CPWD Analysis of Rates · Earth Work

Extra for planking, strutting and packing materials for cavities (in close timbering) if required to be left permanently in position. (Face area of timber permanently left to be measured)

Item number
2.19
Analysis basis
Details of cost for a trench 30m long and
Priced inputs
3
Derived rate
1,692.45 / a trench

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.19 Extra for planking, strutting and packing materials for cavities (in close timbering) if required to be left permanently in position. (Face area of timber permanently left to be measured) — is derived from 3 priced inputs for a trench and works out to ₹1,692.45 per a trench after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.5m deep
  • area 2x30x1.5=90 sqmPoling boards of
  • 90x0.038 = 3.42 cum = 3420 cudm
  • be used once before = 3420 - 427.5 = 2992.5
  • dm
  • Walings 100mmx100mm of
  • 4x30x0.10x0.10 = 1.20cum = 1200 cudm
  • be used once before = 1200 - 150 = 1050
  • dm
  • Struts of
  • and 1.5m long
  • 2x17x1.5 = 51m
  • be used once before = 51 - 6.37 = 44.63 m
  • Less @ 1/8 of Qty as timber is supposed to
  • Less @ 1/8 of Qty as timber is supposed to
  • Less @ 1/8 of Qty as timber is supposed to
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterial10 cudm299.25260.0077,805.00
1197Second ³ class kail wood in scantlingSecond class kail wood in scantlingMaterial10 cudm105260.0027,300.00
0302Safeda ³ ballies 125 mm diameterSafeda ballies 125 mm diameterMaterialmetre44.6344.001,963.72
TOTAL
1,07,068.72
Add 1 % Water charges on "W"
1,070.69
TOTAL
1,08,139.41
Add GST on "X" (multiplying factor 0.2127)
23,001.25
TOTAL
1,31,140.66
Add 15% CPOH on "Y"
19,671.10
TOTAL
1,50,811.76
Add Cess @ 1% on "Z"
1,508.12
Cost of 90 Sqm.
1,52,319.88
Cost per sqm.
1,692.44
Say
1,692.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 117. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.