CPWD Analysis of Rates · Earth Work

Close timbering in case of shafts, wells, cesspits, manholes and the like including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered)

Depth not exceeding 1.5 m

Item number
2.17.1
Analysis basis
Details of cost for 10 manholes 1.2m x 1.0m
Priced inputs
6
Derived rate
151.50 / manholes

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.17.1 Close timbering in case of shafts, wells, cesspits, manholes and the like including strutting, shoring and packing cavities (wherever required) etc. complete. (Measurements to be taken of the face area timbered) Depth not exceeding 1.5 m — is derived from 6 priced inputs for 10 manholes and works out to ₹151.50 per manholes after water charges, GST, CPOH and cess. The full build-up is below.

  • x1.5m
  • Surface area: 10x2x(1.2+1.0)x1.5 = 66 sqm
  • The Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Poling boards of
  • 66x0.038 = 2.51 cum = 2510 cudm
  • Qty taken for cost of using once after
  • deducting for credit = 2510x x = 156.88
  • dm
  • Wallings 100mmx 100mm of ¼ ¼
  • 10x2x2x1.124x0.1x0.1 = 0.45 cum
  • 10x2x2x0.924x0.1x0.1 = 0.37 cum.
  • Total Kail wood = 0.82 cum. = 820dm
  • ³
  • Qty taken for cost of using once after
  • deducting for credit = 820x x = 51.25 dm
  • and 1.50m long ¼ ¼ ³
  • 10x2x2x0.924 = 36.96
  • 10x2x2x0.724 = 28.96
  • Total of balli = 65.92m
  • Qty taken for cost of using once after
  • deducting for credit = 65.92x x = 4.12m
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterial10 cudm15.688260.004,078.88
1197Second ³ class kail wood in scantlingSecond class kail wood in scantlingMaterial10 cudm5.125260.001,332.50
0302Safeda ballies 125 mm diameterMaterialmetre4.1244.00181.28
0112Carpenter 2nd classLabourday0.6816.00489.60
0114Beldar ¼ ¼BeldarLabourday1.2736.00883.20
9999SundriesMaterialL.S.27.32.2761.97
TOTAL
7,027.43
Add 1 % Water charges on “W”
70.27
TOTAL
7,097.70
Add GST on “X” (multiplying factor 0.2127)
1,509.68
TOTAL
8,607.38
Add 15% CPOH on “Y”
1,291.11
TOTAL
9,898.49
Add Cess @ 1% on “Z”
98.98
Cost of 66 sqm.
9,997.47
Cost per sqm.
151.48
Say
151.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 112. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works