CPWD Analysis of Rates · Earth Work

Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered)

Depth exceeding 3 m but not exceeding 4.5 m

Item number
2.16.3
Analysis basis
Details of cost for 10 trench 30m long and
Priced inputs
6
Derived rate
189.65 / trench

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.16.3 Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered) Depth exceeding 3 m but not exceeding 4.5 m — is derived from 6 priced inputs for 10 trench and works out to ₹189.65 per trench after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.5m deep
  • Area 10x2x30x1.5=900 sqmThe Material can be used four times on the
  • same work and after use of material credit is
  • given @ 75% of cost
  • Poling boards of
  • 900x0.038 = 34.2 cum = 34200 cudm
  • Qty taken for cost of using once
  • after deducting for credit = 34200x¼x¼ =
  • 2137.5dm³
  • Wallings 100mmx 100mm of
  • 10x4x30x0.10x0.10 = I2cum = 12000 dm3
  • Qty taken for cost of using once
  • after deducting for credit = 12000x¼x¼ =
  • 750 dm³
  • and 1.5m long
  • 10x2x17x1.5 = 510m
  • Qty taken for cost of using once after
  • deducting for credit = 510x¼x¼ = 31.875 m
CodeInputUnitQuantityRate (INR)Amount (INR)
1198Second class kail wood in planksMaterial10 cudm213.75260.0055,575.00
1197Second class kail wood in scantlingMaterial10 cudm75260.0019,500.00
0302Safeda ballies 125 mm diameterMaterialmetre31.87544.001,402.50
0112Carpenter 2nd classLabourday15816.0012,240.00
0114BeldarLabourday40736.0029,440.00
9999SundriesMaterialL.S.807.32.271,832.57
TOTAL
1,19,990.07
Add 1 % Water charges on “W”
1,199.90
TOTAL
1,21,189.97
Add GST on “X” (multiplying factor 0.2127)
25,777.11
TOTAL
1,46,967.08
Add 15% CPOH on “Y”
22,045.06
TOTAL
1,69,012.14
Add Cess @ 1% on “Z”
1,690.12
Cost of 900 Sqm.
1,70,702.26
Cost per sqm.
189.67
Say
189.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 111. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works