Extra for depth for manholes : Size 90x80 cm

With Sewer bricks conforming to IS : 4885
Item number
19.8.1.2
Analysis basis
one metre
Priced inputs
2
Derived rate
₹8,654.25/ ONE METRE
D-01/RATE ANALYSISITEM 19.8.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.8.1.2 (Extra for depth for manholes : Size 90x80 cm With Sewer bricks conforming to IS : 4885) is derived from 2 priced inputs for one metre and works out to ₹8,654.25 per one metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Brick work with modular extruded brunt
  • fly ash clay sewer bricks conforming to IS
  • : 4885 in cement mortar 1:4 (1 cement : 4
  • coarse sand )
  • 4.32x0.23x1.0 m = 0.994 cum Say 0.99 cum
  • 12 mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • 3.40x1 m = 3.40 sqm
ANALYSIS OF RATES · ITEM 19.8.1.2DETAILS OF COST FOR ONE METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No 6.36.1 of SH : } Brick WorkRate as per item 6.36.1cum0.997,197.757,125.77
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm3.4449.551,528.47
BUILD-UP TO RATE
TOTAL
8,654.24
Cost for one metre
8,654.24
SAY
₹8,654.25
D-02/SOURCEPRINTED PAGE 1724
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1724

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1724. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.