CPWD Analysis of Rates · Drainage
Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete
1800 mm dia RCC pipes. (Laying by manual/ machanical means)
- Item number
- 19.36.6
- Analysis basis
- Detail of cost for 10 metre
- Priced inputs
- 7
- Derived rate
- ₹22,578.75 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.36.6 — Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 1800 mm dia RCC pipes. (Laying by manual/ machanical means) — is derived from 7 priced inputs for 10 metre and works out to ₹22,578.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Detail for 10 metre
- MATERIALS :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1739 | RCC pipe 1800 mm dia pipe NP-4 spigotRCC pipe 1800 mm dia NP-4 spigotMaterial | metre | 10 | 14,605.00 | 1,46,050.00 |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.049 | 5,156.00 | 252.64 |
| 0983 | Fine sand (zone IV)Material | cum | 0.055 | 980.00 | 53.90 |
| 0123 | Mason 1st classMason 1st classLabour | day | 1.15 | 897.00 | 1,031.55 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.15 | 816.00 | 938.40 |
| 0114 | BeldarLabour | day | 13 | 736.00 | 9,568.00 |
| 0101 | BhistiLabour | day | 1 | 816.00 | 816.00 |
- TOTAL
- 1,58,710.49
- Add 1 % Water charges on “W”
- 1,587.10
- TOTAL
- 1,60,297.59
- Add GST on “X” (multiplying factor 0.2127)
- 34,095.30
- TOTAL
- 1,94,392.89
- Add 15% CPOH on “Y”
- 29,158.93
- TOTAL
- 2,23,551.82
- Add Cess @ 1% on “Z”
- 2,235.52
- Rate per metre
- 22,578.73
- Say
- 22,578.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1781. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.