Skip to main content
R/DAR 2023

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1200 mm dia RCC pipes. (Laying by manual/ machanical means)
Item number
19.36.5
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹11,119.35/ METRE
D-01/RATE ANALYSISITEM 19.36.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.36.5 (Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 1200 mm dia RCC pipes. (Laying by manual/ machanical means)) is derived from 7 priced inputs for 10 metre and works out to ₹11,119.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.36.5DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1738MATRCC pipe 1200 mm dia pipe NP-4 spigotRCC pipe 1200 mm dia NP-4 spigotmetre106,965.0069,650.00
0367MATPortland Cement (OPC-43 grade)tonne0.0345,156.00175.30
0983MATFine sand (zone IV)cum0.046980.0045.08
0123LABMason 1st classMason 1st classday0.795897.00713.12
0124LABMason 2nd classMason 2nd classday0.795816.00648.72
0114LABBeldarday8.67736.006,381.12
0101LABBhistiday0.67816.00546.72
BUILD-UP TO RATE
TOTAL
78,160.06
Add 1 % Water charges on “W”
+781.60
TOTAL
78,941.66
Add GST on “X” (multiplying factor 0.2127)
+16,790.89
TOTAL
95,732.55
Add 15% CPOH on “Y”
+14,359.88
TOTAL
1,10,092.43
Add Cess @ 1% on “Z”
+1,100.92
Rate per metre
11,119.34
SAY
₹11,119.35
D-02/SOURCEPRINTED PAGE 1781
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1781

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1781. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.