Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

900 mm dia RCC pipes
Item number
19.36.3
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹7,397.40/ METRE
D-01/RATE ANALYSISITEM 19.36.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.36.3 (Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 900 mm dia RCC pipes) is derived from 7 priced inputs for 10 metre and works out to ₹7,397.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.36.3DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1736MATRCC pipe 900 mm dia pipe NP-4 spigotRCC pipe 900 mm dia NP-4 spigotmetre104,815.0048,150.00
0367MATPortland Cement (OPC-43 grade)tonne0.0255,156.00128.90
0983MATFine sand (zone IV)cum0.033980.0032.34
0123LABMason 1st classMason 1st classday0.625897.00560.63
0124LABMason 2nd classMason 2nd classday0.625816.00510.00
0114LABBeldarday3736.002,208.00
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
51,997.87
Add 1 % Water charges on “W”
+519.98
TOTAL
52,517.85
Add GST on “X” (multiplying factor 0.2127)
+11,170.55
TOTAL
63,688.40
Add 15% CPOH on “Y”
+9,553.26
TOTAL
73,241.66
Add Cess @ 1% on “Z”
+732.42
Rate per metre
7,397.41
SAY
₹7,397.40
D-02/SOURCEPRINTED PAGE 1780
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1780

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1780. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.