Skip to main content
R/DAR 2023

Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

600 mm dia RCC pipes
Item number
19.36.2
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹3,934.75/ METRE
D-01/RATE ANALYSISITEM 19.36.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.36.2 (Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 600 mm dia RCC pipes) is derived from 7 priced inputs for 10 metre and works out to ₹3,934.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.36.2DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1735MATRCC pipe 600 mm dia pipe NP-4 spigotRCC pipe 600 mm dia NP-4 spigotmetre102,515.0025,150.00
0367MATPortland Cement (OPC-43 grade)tonne0.0165,156.0082.50
0983MATFine sand (zone IV)cum0.022980.0021.56
0123LABMason 1st classMason 1st classday0.46897.00412.62
0124LABMason 2nd classMason 2nd classday0.46816.00375.36
0114LABBeldarday1.83736.001,346.88
0101LABBhistiday0.33816.00269.28
BUILD-UP TO RATE
TOTAL
27,658.20
Add 1 % Water charges on “W”
+276.58
TOTAL
27,934.78
Add GST on “X” (multiplying factor 0.2127)
+5,941.73
TOTAL
33,876.51
Add 15% CPOH on “Y”
+5,081.48
TOTAL
38,957.99
Add Cess @ 1% on “Z”
+389.58
Rate per metre
3,934.76
SAY
₹3,934.75
D-02/SOURCEPRINTED PAGE 1779
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1779

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1779. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.