CPWD Analysis of Rates · Drainage
Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge
Rectangular arch type manhole 140x90 cm and 2.45 m deep
- Item number
- 19.24.3
- Analysis basis
- Details of cost of a manhole 140x90 cm
- Priced inputs
- 6
- Derived rate
- ₹8,466.35
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.24.3 — Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge: Rectangular arch type manhole 140x90 cm and 2.45 m deep — is derived from 6 priced inputs and works out to ₹8,466.35 after water charges, GST, CPOH and cess. The full build-up is below.
- and 2.45 m deep
- Dismantling of cement concrete 1:4:8 (1
- cement : 4 coarse sand 8 : aggregate
- stone 40 mm nominal size)
- 2.16m x 1.66m x 0.20m = 0.72 cum
- Dismantling of second class brick work in
- cement mortar 1:4 (1 cement : 4 coarse
- sand)
- Brick work in item 5.52mx0.23mx1.20m =
- 1.524 cum
- 3.92mx0.23mx1.15m = 1.037 cum =
- 2.561 cum
- 2x½x3.14x0.25mx0.23x0.1m = 0.018
- cum
- 2x3.14/4(0.15)²x0.23m = 0.008 cum = (-)
- 0.026 cum
- Net qty = 2.561 - 0.026 = 2.535 cum
- Brick work in arch
- ½x3.14x1.13x0.80x0.23m = 0.327 cum
- 2x½x3.14x0.25mx0.23x0.1m = 0.018
- cum
- = 0.345 cum Say 0.35 cum
- Net qty = 2.54+0.35 = 2.89 cum
- Dismantling cement concrete 1:2:4 ( 1
- cement : 2 coarse sand : 4 graded stone
- aggregate 20 mm nominal size)
- 2x1.4x0.90/2x(0.20+0.30)/2 = 0.315 cum
- cum
- Net qty = 0.290 cum
- Dismantling of R.C.C slab of 1:2:4 (1
- cement : 2 coarse sand : 4 grade stone
- aggregate 20 mm nominal size)
- 1.36mx1.06mx0.15 = 0.216 cum
- 0.029 cum
- = 0.187 cum Say 0.19 cum
- Deduct arch ring and portion of pipe
- Say 2.54 cum
- Less pipe 1.4x3.14/4x(0.15)² = (-) 0.025
- Less cover 3.14/4x(0.50)²x0.15m = (-)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no. 15.2.2 of SH : Dismantling and demolishingRate as per item 15.2.2Sub-analysis | cum | 0.72 | 1,503.60 | 1,082.59 | |
| Rate as per item no. 15.7.4 of SH :dismantling and dimolishingRate as per item 15.7.4Sub-analysis | cum | 2.89 | 2,060.20 | 5,953.98 | |
| Rate as per item no. 15.2.1 of SH : Dismantling and demolishingRate as per item 15.2.1Sub-analysis | cum | 0.29 | 2,434.25 | 705.93 | |
| Rate as per item no 15.3 of SH : Demolishing and dismantlingRate as per item 15.3Sub-analysis | cum | 0.19 | 3,551.25 | 674.74 | |
| 9999 | Removal of C.I. Cover with frameMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 9999 | Removal of M.S foot restMaterial | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 8,451.77
- Add 1 % Water charges on “W-A”
- 0.35
- TOTAL
- 8,452.12
- Add GST on “X-A” (multiplying factor 0.2127)
- 7.42
- TOTAL
- 8,459.54
- Add 15% CPOH on “Y-A”
- 6.34
- TOTAL
- 8,465.88
- Add Cess @ 1% on “Z-A”
- 0.49
- Cost of one no
- 8,466.37
- Say
- 8,466.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1756. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.