CPWD Analysis of Rates · Drainage
Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge
Rectangular manhole 120x90 cm and 90 cm deep
- Item number
- 19.24.2
- Analysis basis
- Details of cost of a manhole 120x90 and
- Priced inputs
- 5
- Derived rate
- ₹4,475.50
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.24.2 — Dismantling of manhole including R.C.C. top slab, C.I. cover with frame, including stacking of useful materials near the site and disposal of unserviceable materials within 50 m lead as per direction of Engineer-in-charge: Rectangular manhole 120x90 cm and 90 cm deep — is derived from 5 priced inputs and works out to ₹4,475.50 after water charges, GST, CPOH and cess. The full build-up is below.
- 90 cm deep
- Dismantling of cement concrete 1:4:8 (1
- cement : 4 coarse sand 8 : aggregate
- stone 40 mm nominal size)
- 1.81x1.51x0.20 m = 0.547 cum Say 0.55
- cum
- Dismantling of secon class brick work in
- cement mortar 1:4 (1 cement : 4 coarse
- sand)
- 5.12x0.23x0.80 m = 0.942 cum
- (-) 0.008 cum
- Net qty = 0.934 cum Say 0.93 cum
- Dismantling cement concrete 1:2:4 ( 1
- cement : 2 coarse sand : 4 graded stone
- aggregate 20 mm nominal size)
- 2x1.20x0.90x(0.80/2) x (0.30+0.20)/2 =
- 2.70 cum
- 0.021 cum
- = 0.249 cum say 0.25
- Dismantling of R.C.C slab of 1:2:4 (1
- cement : 2 coarse sand : 4 grade stone
- aggregate 20 mm nominal size)
- For slab : 1.66x1.36x0.15m = 0.339 cum
- 0.029 cum
- Net qty = 0.31 cum
- Less for pipe 2x3.14x(0.15m)²x0.23 m =
- Less for pipe 1.20x3.14/4x(0.15m)² = (-)
- Less for cover 3.14/4x(0.50)²x0.15m = (-)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per item no. 15.2.2 of SH : Dismantling and demolishingRate as per item 15.2.2Sub-analysis | cum | 0.55 | 1,503.60 | 826.98 | |
| Rate as per item no. 15.7.4 of SH :dismantling and dimolishingRate as per item 15.7.4Sub-analysis | cum | 0.93 | 2,060.20 | 1,915.99 | |
| Rate as per item no. 15.2.1 of SH : Dismantling and demolishingRate as per item 15.2.1Sub-analysis | cum | 0.25 | 2,434.25 | 608.56 | |
| Rate as per item no 15.3 of SH : Demolishing and dismantlingRate as per item 15.3Sub-analysis | cum | 0.31 | 3,551.25 | 1,100.89 | |
| 9999 | Removal of C.I. Cover with frameMaterial | L.S. | 7.15 | 2.27 | 16.23 |
- TOTAL
- 4,468.65
- Add 1 % Water charges on “W-A”
- 0.16
- TOTAL
- 4,468.81
- Add GST on “X-A” (multiplying factor 0.2127)
- 3.49
- TOTAL
- 4,472.30
- Add 15% CPOH on “Y-A”
- 2.98
- TOTAL
- 4,475.28
- Add Cess @ 1% on “Z-A”
- 0.23
- Cost of one no
- 4,475.51
- Say
- 4,475.50
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1755. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works