Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe and bend encased all-round with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) with all centering and shuttering required, cutting holes in walls and making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall, lead caulked joints between sand cast iron pipes and fittings, stiff cement mortar 1:1 (1 cement : 1 fine sand) joints between sand cast iron tee and S.W. pipe, making required channels complete as per standard design and specifications

100 mm dia sand cast iron drop connection
Item number
19.22.1
Analysis basis
one drop
Priced inputs
16
Derived rate
₹12,172.05/ ONE DROP
D-01/RATE ANALYSISITEM 19.22.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.22.1 (Providing sand cast iron drop connection externally for 60 cm drop from branch sewer line to main sewer manhole including inspection and cleaning eye with chain and lid, sand cast iron drop pipe and bend encased all-round with cement concrete 1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size) with all centering and shuttering required, cutting holes in walls and making good with brick work in cement mortar 1:4 (1 cement : 4 coarse sand) plastered with cement mortar 1:3 (1 cement : 3 coarse sand) on inside of the manhole wall, lead caulked joints between sand cast iron pipes and fittings, stiff cement mortar 1:1 (1 cement : 1 fine sand) joints between sand cast iron tee and S.W. pipe, making required channels complete as per standard design and specifications : 100 mm dia sand cast iron drop connection) is derived from 16 priced inputs for one drop and works out to ₹12,172.05 per one drop after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • = 37+30+33 =101 cm =1.00 m
  • Length of pipe = 1.00 m. Hence, Qty =
  • 1.00 /1.8 =0.556 Nos
  • Cutting charges
  • Brick work in cement mortar 1:4 (1 cement : 4 coarse sand)
  • 0.20x0.20x0.23 = 0.009 cum
  • 0.002 cum
  • Net Qty= 0.009 - 0.002 = 0.007 cum
  • Cement concrete 1:5:10 (1 cement : 5
  • fine sand : 10 graded stone aggregate 40
  • mm nominal size)
  • 0.40x0.45x1.05 m = 0.189 cum
  • 0.40x0.25x0.40 = 0.040 cum
  • Total= 0.229 cum
  • 1/2x3.14x0.10x0.10x1.50 = 0.012 cum
  • Toothing portion
  • 2x0.40x0.05x0.10 m = 0.004 cum =
  • 0.016 cum
  • Net Qty= 0.229-0.016 = 0.213 cum Say
  • 0.21 cum
  • 12 mm cement plaster 1:3 (1 cement : 3
  • coarse sand) finished with floating coat of
  • neat cement
  • 1x0.25x0.25 m = 0.0625 Say 0.06 sqm
  • Providing lead caulked joints to 100 mm
  • diameter pipe and special
  • Form work
  • 1.30x1.05 m = 1.36 sqm
  • For cutting holes 5 cm deep in alternate course of brick work benching and
  • channel
  • Less pipe 1/2x3.14x0.10x0.10x0.23 =
  • Less pipe portion
ANALYSIS OF RATES · ITEM 19.22.1DETAILS OF COST FOR ONE DROP CONNECTION
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1617MATS.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 100mm diaS.C.I. soil, waste and vent single socketed pipe 1.80 metres long:100 mm diaeach0.5561,200.00667.20
9977MATCarriage of pipeL.S.1.432.273.25
SUBRate as per item no 18.83.2 of SH: Water supplyRate as per item 18.83.2each cut3194.70584.10
1336MATClearing eye with chain and lid 100 mm diaeach150.0050.00
1621MATS.C.I. plain bend 100 mm diaeach1300.00300.00
1628MATS.C.I. plain single equal junctions 100x100x100 mm diaeach1410.00410.00
SUBRate as per item no 6.1.1 of SH : Brick WorkRate as per item 6.1.1cum0.0077,370.6551.59
SUBRate as per item no 4.1.11 of SH : Concrete WorkRate as per item 4.1.11cum0.216,189.651,299.83
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm0.06449.5526.97
SUBRate as per item no. 12.39.1 of SH : RoofingRate as per item 12.39.1each4580.502,322.00
9999MATProviding joint to S.W. pipe with cement mortar 1:1 (1 cement : 1 fine sand)L.S.26.912.2761.09
SUBRate as per item no 5.9.2 of SH : RCCRate as per item 5.9.2sqm1.36842.501,145.80
9988MATSundries including carriage of bends etc.L.S.26.912.2761.09
0123LABMason 1st classMason 1st classday0.7897.00627.90
0124LABMason 2nd classMason 2nd classday0.7816.00571.20
0114LABBeldarday2.7736.001,987.20
BUILD-UP TO RATE
TOTAL
10,169.22
Add 1 % Water charges on “W-A”
+47.39
TOTAL
10,216.61
Add GST on “X-A” (multiplying factor 0.2127)
+1,018.05
TOTAL
11,234.66
Add 15% CPOH on “Y-A”
+870.66
TOTAL
12,105.32
Add Cess @ 1% on “Z-A”
+66.75
Cost of one drop connection
12,172.07
SAY
₹12,172.05
D-02/SOURCEPRINTED PAGE 1749
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1749

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1749. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE