Skip to main content
R/DAR 2023

Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete

For pipes 350 to 450 mm diameter
Item number
19.21.3
Analysis basis
one connection
Priced inputs
6
Derived rate
₹1,328.45/ ONE CONNECTION
D-01/RATE ANALYSISITEM 19.21.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.21.3 (Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : For pipes 350 to 450 mm diameter) is derived from 6 priced inputs for one connection and works out to ₹1,328.45 per one connection after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4 mix ( 1 cement :
  • 2 coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • = 0.50x0.50x0.30 m = 0.075 cum
  • 0.048 cum
  • = 0.027 cum Say 0.03 cum
  • 12 mm cement plater 1:3 ( 1 cement : 3
  • coarse sand ) finished with a floating coat
  • of neat cement
  • 2x0.55x0.55 =0.605 sqm Say 0.60 sqm
  • (For cutting holes average size 30x30 cm
  • in 23 cm thick wall and making channel
  • etc.)
  • Less pipe = 1/2x3.14x0.45x0.45x0.30 =
ANALYSIS OF RATES · ITEM 19.21.3DETAILS OF COST FOR ONE CONNECTION
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.037,878.50236.36
SUBRate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1sqm0.6449.55269.73
0123LABMason 1st classMason 1st classday0.16897.00143.52
0124LABMason 2nd classMason 2nd classday0.16816.00130.56
0114LABBeldarday0.33736.00242.88
9999MATAdd for delay sundries etc.L.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
1,084.14
Add 1 % Water charges on “W-A”
+5.78
TOTAL
1,089.92
Add GST on “X-A” (multiplying factor 0.2127)
+124.18
TOTAL
1,214.10
Add 15% CPOH on “Y-A”
+106.20
TOTAL
1,320.30
Add Cess @ 1% on “Z-A”
+8.14
Cost for 1 connection
1,328.44
SAY
₹1,328.45
D-02/SOURCEPRINTED PAGE 1749
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1749

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1749. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.