Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete
- Item number
- 19.21.1
- Analysis basis
- one connection
- Priced inputs
- 6
- Derived rate
- ₹810.45/ ONE CONNECTION
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.21.1 (Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : For pipes 100 to 250 mm diameter) is derived from 6 priced inputs for one connection and works out to ₹810.45 per one connection after water charges, GST, CPOH and cess. The full build-up is below.
- cement concrete 1:2:4 mix (1 cement : 2
- coarse sand : 4 graded stone aggregate
- 20 mm nominal size)
- = 0.30x0.30x0.23 m = 0.0207 cum
- 0.0096 cum
- = 0.0111 cum Say 0.01 cum
- 12 mm cement plater 1:3 ( 1 cement : 3
- coarse sand ) finished with a floating coat
- of neat cement
- 2x0.35x0.35 =0.25sqm
- (For cutting holes average size 30x30 cm in
- 23 cm thick wall and making channel etc.)
- Less pipe = 1/2x3.14x0.23x0.23x0.23 =
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item no. 4.1.3 of SH : ConcreteRate as per item 4.1.3 | cum | 0.01 | 7,878.50 | 78.79 | |
| SUB | Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1 | sqm | 0.25 | 449.55 | 112.39 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.12 | 897.00 | 107.64 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.12 | 816.00 | 97.92 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 9999 | MAT | Add for delay sundries etc. | L.S. | 20.15 | 2.27 | 45.74 |
- TOTAL
- 626.48
- Add 1 % Water charges on “W-A”
- +4.35
- TOTAL
- 630.83
- Add GST on “X-A” (multiplying factor 0.2127)
- +93.51
- TOTAL
- 724.34
- Add 15% CPOH on “Y-A”
- +79.97
- TOTAL
- 804.31
- Add Cess @ 1% on “Z-A”
- +6.13
- Cost for 1 connection
- 810.44
- SAY
- ₹810.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1747
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1747. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.