Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete

For pipes 100 to 250 mm diameter

Item number
19.21.1
Analysis basis
Details of cost for one connection
Priced inputs
6
Derived rate
810.45 / one connection

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.21.1 Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : For pipes 100 to 250 mm diameter — is derived from 6 priced inputs for one connection and works out to ₹810.45 per one connection after water charges, GST, CPOH and cess. The full build-up is below.

  • cement concrete 1:2:4 mix (1 cement : 2
  • coarse sand : 4 graded stone aggregate
  • 20 mm nominal size)
  • = 0.30x0.30x0.23 m = 0.0207 cum
  • 0.0096 cum
  • = 0.0111 cum Say 0.01 cum
  • 12 mm cement plater 1:3 ( 1 cement : 3
  • coarse sand ) finished with a floating coat
  • of neat cement
  • 2x0.35x0.35 =0.25sqm
  • (For cutting holes average size 30x30 cm in
  • 23 cm thick wall and making channel etc.)
  • Less pipe = 1/2x3.14x0.23x0.23x0.23 =
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no. 4.1.3 of SH : ConcreteRate as per item 4.1.3Sub-analysiscum0.017,878.5078.79
Rate as per item no 13.9.1 of SH : FinishingRate as per item 13.9.1Sub-analysissqm0.25449.55112.39
0123Mason 1st classMason 1st classLabourday0.12897.00107.64
0124Mason 2nd classMason 2nd classLabourday0.12816.0097.92
0114BeldarLabourday0.25736.00184.00
9999Add for delay sundries etc.MaterialL.S.20.152.2745.74
TOTAL
626.48
Add 1 % Water charges on “W-A”
4.35
TOTAL
630.83
Add GST on “X-A” (multiplying factor 0.2127)
93.51
TOTAL
724.34
Add 15% CPOH on “Y-A”
79.97
TOTAL
804.31
Add Cess @ 1% on “Z-A”
6.13
Cost for 1 connection
810.44
Say
810.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1747. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.