Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality EHD - 35

Circular shape 560 mm internal dia
Item number
19.19.4.1
Analysis basis
one no
Priced inputs
4
Derived rate
₹2,123.80/ ONE NO
D-01/RATE ANALYSISITEM 19.19.4.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.4.1 (Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality EHD - 35 Circular shape 560 mm internal dia) is derived from 4 priced inputs for one no and works out to ₹2,123.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:2:4 ( 1 cement : 2
  • coarse sand : 4 grade stone aggregate
  • 20 mm nominal size )
  • 3.14/4x(1.05)²x0.15 = 0.1299 cum
  • 3.14/4x(0.9)²x0.15 = (-) 0.0955 cum
  • = 0.0344 cum Say 0.03 cum
  • Less cover with frame
ANALYSIS OF RATES · ITEM 19.19.4.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7136MATCircular shape 560 mm dia precast R.C.C. manhole cover with frame - E.H.D. - 35each11,250.001,250.00
9977MATCarriage of manhole coverL.S.13.522.2730.69
SUBRate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3cum0.037,878.50236.36
9999MATSundriesL.S.20.282.2746.04
BUILD-UP TO RATE
TOTAL
1,563.09
Add 1 % Water charges on “W-A”
+13.27
TOTAL
1,576.36
Add GST on “X-A” (multiplying factor 0.2127)
+285.02
TOTAL
1,861.38
Add 15% CPOH on “Y-A”
+243.75
TOTAL
2,105.13
Add Cess @ 1% on “Z-A”
+18.69
Cost for 1 no.
2,123.82
SAY
₹2,123.80
D-02/SOURCEPRINTED PAGE 1746
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1746

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1746. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.