Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality EHD - 35
- Item number
- 19.19.4.1
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹2,123.80/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.19.4.1 (Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality EHD - 35 Circular shape 560 mm internal dia) is derived from 4 priced inputs for one no and works out to ₹2,123.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:2:4 ( 1 cement : 2
- coarse sand : 4 grade stone aggregate
- 20 mm nominal size )
- 3.14/4x(1.05)²x0.15 = 0.1299 cum
- 3.14/4x(0.9)²x0.15 = (-) 0.0955 cum
- = 0.0344 cum Say 0.03 cum
- Less cover with frame
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7136 | MAT | Circular shape 560 mm dia precast R.C.C. manhole cover with frame - E.H.D. - 35 | each | 1 | 1,250.00 | 1,250.00 |
| 9977 | MAT | Carriage of manhole cover | L.S. | 13.52 | 2.27 | 30.69 |
| SUB | Rate as per item no. 4.1.3 of SH : Concrete WorkRate as per item 4.1.3 | cum | 0.03 | 7,878.50 | 236.36 | |
| 9999 | MAT | Sundries | L.S. | 20.28 | 2.27 | 46.04 |
- TOTAL
- 1,563.09
- Add 1 % Water charges on “W-A”
- +13.27
- TOTAL
- 1,576.36
- Add GST on “X-A” (multiplying factor 0.2127)
- +285.02
- TOTAL
- 1,861.38
- Add 15% CPOH on “Y-A”
- +243.75
- TOTAL
- 2,105.13
- Add Cess @ 1% on “Z-A”
- +18.69
- Cost for 1 no.
- 2,123.82
- SAY
- ₹2,123.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1746
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1746. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.