Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910, on 12 mm dia steel bar conforming to IS: 1786, having minimum cross section as 23 mmx25 mm and over all minimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) complete as per design

Item number
19.16
Analysis basis
one no
Priced inputs
6
Derived rate
₹553.70/ ONE NO
D-01/RATE ANALYSISITEM 19.16

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.16 (Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910, on 12 mm dia steel bar conforming to IS: 1786, having minimum cross section as 23 mmx25 mm and over all minimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) complete as per design) is derived from 6 priced inputs for one no and works out to ₹553.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement concrete 1:3:6 (1 Cement : 3
  • coarse sand : 6 graded stone aggregate
  • 20 mm nominal size)
  • ( 0.30x0.20x0.15 = 0.009 cum)
ANALYSIS OF RATES · ITEM 19.16DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7354MATPlastic encapsuled M.S. foot rest 30x20x15 cmPlastic encapsulated M.S. foot rest 30x20x15 cmeach1121.00121.00
9988MATCarriage and other sundriesL.S.1.822.274.13
SUBRate as per item no 4.1.5 of SH : Concrete workRate as per item 4.1.5cum0.0097,294.7065.65
0123LABMason 1st classMason 1st classday0.02897.0017.94
0124LABMason 2nd classMason 2nd classday0.2816.00163.20
0114LABBeldarday0.05736.0036.80
BUILD-UP TO RATE
TOTAL
408.72
Add 1 % Water charges on “W-A”
+3.43
TOTAL
412.15
Add GST on “X-A” (multiplying factor 0.2127)
+73.70
TOTAL
485.85
Add 15% CPOH on “Y-A”
+63.03
TOTAL
548.88
Add Cess @ 1% on “Z-A”
+4.83
Cost for 1 no.
553.71
SAY
₹553.70
D-02/SOURCEPRINTED PAGE 1740
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1740

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1740. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE