Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910, on 12 mm dia steel bar conforming to IS: 1786, having minimum cross section as 23 mmx25 mm and over all minimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) complete as per design
- Item number
- 19.16
- Analysis basis
- one no
- Priced inputs
- 6
- Derived rate
- ₹553.70/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.16 (Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910, on 12 mm dia steel bar conforming to IS: 1786, having minimum cross section as 23 mmx25 mm and over all minimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) complete as per design) is derived from 6 priced inputs for one no and works out to ₹553.70 per one no after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:3:6 (1 Cement : 3
- coarse sand : 6 graded stone aggregate
- 20 mm nominal size)
- ( 0.30x0.20x0.15 = 0.009 cum)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7354 | MAT | Plastic encapsuled M.S. foot rest 30x20x15 cmPlastic encapsulated M.S. foot rest 30x20x15 cm | each | 1 | 121.00 | 121.00 |
| 9988 | MAT | Carriage and other sundries | L.S. | 1.82 | 2.27 | 4.13 |
| SUB | Rate as per item no 4.1.5 of SH : Concrete workRate as per item 4.1.5 | cum | 0.009 | 7,294.70 | 65.65 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.02 | 897.00 | 17.94 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.2 | 816.00 | 163.20 |
| 0114 | LAB | Beldar | day | 0.05 | 736.00 | 36.80 |
- TOTAL
- 408.72
- Add 1 % Water charges on “W-A”
- +3.43
- TOTAL
- 412.15
- Add GST on “X-A” (multiplying factor 0.2127)
- +73.70
- TOTAL
- 485.85
- Add 15% CPOH on “Y-A”
- +63.03
- TOTAL
- 548.88
- Add Cess @ 1% on “Z-A”
- +4.83
- Cost for 1 no.
- 553.71
- SAY
- ₹553.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1740
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1740. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.