CPWD Analysis of Rates · Conservation of Heritage Buildings
Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/ structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose. (2) The payment will be made once only for execution of all items for such works
- Item number
- 24.2
- Analysis basis
- Details of cost for area 22.5x9.0=202.50 sqm
- Priced inputs
- 10
- Derived rate
- ₹338.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 24.2 — Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/ structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for execution of work of cleaning and/ or pointing and/ or applying chemical and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connecting with the building etc, wherever required, if feasible, for inspection of work at required locations with essential safety features for the workmen etc., complete as per directions and approval of Engineer-in-charge. Note:- (1) The elevational area of the scaffolding shall be measured for payment purpose. (2) The payment will be made once only for execution of all items for such works — is derived from 10 priced inputs for area 22 and works out to ₹338.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Assuming shuttering material will become unserviceable after use of 40 times Adding for maintenance @ 10% of cost
- Taking slvage value after full use of material @
- 25% of cost
- Qty taken for cost of using once
- =14x0.85/40=0.2975
- Vertical standard 2.5m length=7x2x9x2.5=315.00 m
- Side support 6.00m length=3x2x6.00=36.00m
- Horizonatal support 3.00mlength=18x3x3.00=162.00m
- Total=1026.00m
- @ 3.67 kg/m =3765.42 kgQty taken for
- 7x2x9=126 nos x 0.40m length = 50.40m @2.46kg
- /m=123.98kgQty taken for cost of using once=
- 123.98x0.85/40=2.63kg
- 2x7x2x9=252 nos @ 0.15 kg each=37.80 kg
- =0.378qQty taken for cost of using once=
- 0.378x0.85/40=0.008q
- Clamp coupler for fixing MS tube with scafolding
- 2x3x2+2x18x3=120 nosQty taken for cost of using
- once= 120x0.85/40=2.55 nos
- 3 nos x 18 lines=54 nosTwo level plate challies=2x18 lines=36nosTotal=90 nos
- Qty taken for cost of using once=90x0.85/40=1.9125 nos
- For Vertical standards=(5x7x2x9=630 nos)
- +(2x18x19=694 nos)Total=1314 nos
- Qty taken for cost of using once=
- 1314x0.85/40=27.92
- 40mm dia MS pipe=3765.42kg
- 25mm spigot=123.98kgNuts &
- bolts=37.80kgclamp=120 nos@1.00kg
- each=120.00kgChallies=90 nos @ 15.00kg
- each=1350.00kgCup locks=1314 nos @
- 0.50kg each=
- 657.00kgTotal=6054.20kg=6.054 tonne
- cost of using once= 3765.42x0.85/40=80.02kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7397 | Base jackMaterial | each | 0.3 | 155.00 | 46.50 |
| 4009 | Mild steel tubes hot finished welded typeMaterial | kilogram | 80.02 | 72.00 | 5,761.44 |
| 7387 | Spigot for standard jointingMaterial | kg | 2.63 | 44.00 | 115.72 |
| 1034 | Bolts and nuts upto 300 mm in lengthBolts and nuts up to 300 mm in lengthMaterial | quintal | 0.008 | 5,200.00 | 41.60 |
| 7346 | Double couplerMaterial | each | 2.55 | 49.00 | 124.95 |
| 7398 | ChalliesMaterial | each | 1.91 | 834.00 | 1,592.94 |
| 7399 | Cup lockCup locksMaterial | each | 27.92 | 50.00 | 1,396.00 |
| 0116 | Fitter (grade 1)Labour | day | 15.5 | 897.00 | 13,903.50 |
| 0114 | BeldarLabour | day | 31 | 736.00 | 22,816.00 |
| 9999 | SundriesMaterial | L.S. | 1,035 | 2.27 | 2,349.45 |
- TOTAL
- 48,148.10
- Add 1 % Water charges on “W”
- 481.48
- TOTAL
- 48,629.58
- Add GST on “X” (multiplying factor 0.2127)
- 10,343.51
- TOTAL
- 58,973.09
- Add 15% CPOH on “Y”
- 8,845.96
- TOTAL
- 67,819.05
- Add Cess @ 1% on “Z”
- 678.19
- Cost of 202.50 sqm
- 68,497.24
- Cost of 1.00 sqm
- 338.26
- Say
- 338.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1889. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works