Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete

1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)

Item number
4.6.1A
Analysis basis
Details of cost for 250 no kerbs, 40x30x20cm
Priced inputs
5
Derived rate
8,514.85 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.6.1A Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%) — is derived from 5 priced inputs for 250 no and works out to ₹8,514.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

  • 250 no x 0.40m x 0.30m x 0.20m = 6 cum
  • Cement concrete 1:1.5:3
  • Centering and shuttering
  • (1) Mould
  • (i) Plate 3mm thick
  • 10x0.28 sqm. @ 23.55kg/m = 65.9 kg.
  • (ii) Flat 10x5mm
  • Handle ²
  • 10x2x0.25 x0.4 = 2kg. Total =67.9 kg
  • Assuming shuttering will become unserviceable
  • after use of 40 times and taking 75% credit.
  • Qty taken for cost of using once = 67.9x0.75/40
  • = 1.273 kg
  • (2) Moulding Platform
  • Assuming platform will become unserviceable
  • after use of 40 times.
  • (i) Brick on edge flooring cement mortar 1:6
  • 10x1x2.0x2.0m = 40 sqm.
  • Qty taken for cost of using once = 40/40 = 1 sqm
  • (ii) 25mm thick cement concrete 1:2:4 in pavement
  • 10x2.00x2.00x0.025 = 1
  • Qty taken for cost of using once = 1/40 = 0.025
  • cum
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2ASub-analysiscum68,127.8048,766.80
Rate as per item No. 10.1 SH: Steel workRate as per item 10.1Sub-analysiskg1.273117.35149.39
Rate as per item No. 11.1.2 SH: Flooring work.Rate as per item 11.1.2Sub-analysissqm1965.55965.55
Rate as per item No. Sub AR-1 (Reference item no 11.7)Rate as per item Sub A/R-1Sub-analysiscum0.0258,844.45221.11
9999Mortar and labour for finishingMaterialL.S.305.42.27693.26
TOTAL
50,796.11
Add 1 % Water charges on “W-A”
6.93
TOTAL
50,803.04
Add GST on “X-A” (multiplying factor 0.2127)
148.93
TOTAL
50,951.97
Add 15% CPOH on “Y-A”
127.37
TOTAL
51,079.34
Add Cess @ 1% on “Z-A”
9.76
Cost for 6 cum.
51,089.10
Cost per cum.
8,514.85
Say
8,514.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 175. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.