Skip to main content
R/DAR 2023

Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete

1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)
Item number
4.6.1A
Analysis basis
250 no
Priced inputs
5
Derived rate
₹8,514.85/ NO
D-01/RATE ANALYSISITEM 4.6.1A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.6.1A (Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering complete 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)) is derived from 5 priced inputs for 250 no and works out to ₹8,514.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 250 no x 0.40m x 0.30m x 0.20m = 6 cum
  • Cement concrete 1:1.5:3
  • Centering and shuttering
  • (1) Mould
  • (i) Plate 3mm thick
  • 10x0.28 sqm. @ 23.55kg/m = 65.9 kg.
  • (ii) Flat 10x5mm
  • Handle ²
  • 10x2x0.25 x0.4 = 2kg. Total =67.9 kg
  • Assuming shuttering will become unserviceable
  • after use of 40 times and taking 75% credit.
  • Qty taken for cost of using once = 67.9x0.75/40
  • = 1.273 kg
  • (2) Moulding Platform
  • Assuming platform will become unserviceable
  • after use of 40 times.
  • (i) Brick on edge flooring cement mortar 1:6
  • 10x1x2.0x2.0m = 40 sqm.
  • Qty taken for cost of using once = 40/40 = 1 sqm
  • (ii) 25mm thick cement concrete 1:2:4 in pavement
  • 10x2.00x2.00x0.025 = 1
  • Qty taken for cost of using once = 1/40 = 0.025
  • cum
ANALYSIS OF RATES · ITEM 4.6.1ADETAILS OF COST FOR 250 NO KERBS, 40X30X20CM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.4.1.2A of SH:Concrete WorkRate as per item 4.1.2Acum68,127.8048,766.80
SUBRate as per item No. 10.1 SH: Steel workRate as per item 10.1kg1.273117.35149.39
SUBRate as per item No. 11.1.2 SH: Flooring work.Rate as per item 11.1.2sqm1965.55965.55
SUBRate as per item No. Sub AR-1 (Reference item no 11.7)Rate as per item Sub A/R-1cum0.0258,844.45221.11
9999MATMortar and labour for finishingL.S.305.42.27693.26
BUILD-UP TO RATE
TOTAL
50,796.11
Add 1 % Water charges on “W-A”
+6.93
TOTAL
50,803.04
Add GST on “X-A” (multiplying factor 0.2127)
+148.93
TOTAL
50,951.97
Add 15% CPOH on “Y-A”
+127.37
TOTAL
51,079.34
Add Cess @ 1% on “Z-A”
+9.76
Cost for 6 cum.
51,089.10
Cost per cum.
8,514.85
SAY
₹8,514.85
D-02/SOURCEPRINTED PAGE 175
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
175

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 175. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.