Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing
- Item number
- 4.2.5B
- Analysis basis
- 1 cum
- Priced inputs
- 14
- Derived rate
- ₹7,656.55/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.2.5B (Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:3:6 (1 cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Aggregate (RA))) is derived from 14 priced inputs for 1 cum and works out to ₹7,656.55 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (Extra labour for lifting material upto floor V
- level = 0.75 x 2.0 = 1.50)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0283 | MAT | Recycled Aggregate (RA) 40 mm nominal sizeRecycled Aggregate (RA) 20 mm nominal size | cum | 0.7 | 420.00 | 294.00 |
| 0284 | MAT | Recycled Aggregate (RA) 20 mm nominal sizeRecycled Aggregate (RA) 10 mm nominal size | cum | 0.24 | 450.00 | 108.00 |
| 0278 | MAT | Manufactured sand derived from Recycled Concrete Aggregate (RCA) | cum | 0.47 | 957.00 | 449.79 |
| 0367 | MAT | Portland Cement (0.15674 cum)Portland Cement (OPC-43 Grade) | tonne | 0.22 | 5,156.00 | 1,134.32 |
| 0114 | LAB | Beldar | day | 0.9 | 736.00 | 662.40 |
| 0115 | LAB | Coolie | day | 0.78 | 736.00 | 574.08 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0123 | LAB | Mason (brick layer) 1st classMason 1st class | day | 0.06 | 897.00 | 53.82 |
| 0124 | LAB | Mason (brick layer) 2nd classMason 2nd class | day | 0.06 | 816.00 | 48.96 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Scaffolding | L.S. | 114.4 | 2.27 | 259.69 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
| 0115 | LAB | Coolie | day | 1.5 | 736.00 | 1,104.00 |
- TOTAL
- 5,381.95
- Add 1 % Water charges on “W”
- +53.82
- TOTAL
- 5,435.77
- Add GST on “X” (multiplying factor 0.2127)
- +1,156.19
- TOTAL
- 6,591.96
- Add 15% CPOH on “Y”
- +988.79
- TOTAL
- 7,580.75
- Add Cess @ 1% on “Z”
- +75.81
- Cost of 1 cum.
- 7,656.56
- SAY
- ₹7,656.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 166
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 166. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate