CPWD Analysis of Rates · Concrete Work

Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing

1:3:6 (1 cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA))

Item number
4.2.5A
Analysis basis
Details of cost for 1 cum.
Priced inputs
14
Derived rate
8,364.45 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.2.5A Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:3:6 (1 cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 6 graded stone aggregate 20 mm nominal size Recycled Concrete Aggregate (RCA)) — is derived from 14 priced inputs for 1 cum and works out to ₹8,364.45 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • (Extra labour for lifting material upto floor V
  • level = 0.75 x 2.0 = 1.50)
CodeInputUnitQuantityRate (INR)Amount (INR)
0279Recycled Concrete Aggregate (RCA) 20 mm nominal sizeMaterialcum0.7957.00669.90
0281Recycled Concrete Aggregate (RCA) 10 mm nominal sizeMaterialcum0.24957.00229.68
0278Manufactured sand derived from Recycled Concrete Aggregate (RCA)Materialcum0.47957.00449.79
0367Portland Cement (0.15674 cum)Portland Cement (OPC-43 Grade)Materialtonne0.225,156.001,134.32
0114BeldarLabourday0.9736.00662.40
0115CoolieLabourday0.78736.00574.08
0101BhistiLabourday0.7816.00571.20
0123Mason (brick layer) 1st classMason 1st classLabourday0.06897.0053.82
0124Mason (brick layer) 2nd classMason 2nd classLabourday0.06816.0048.96
0002Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachineryday0.07900.0063.00
0012Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machineryday0.07400.0028.00
9999ScaffoldingMaterialL.S.114.42.27259.69
9999SundriesMaterialL.S.13.522.2730.69
0115CoolieLabourday1.5736.001,104.00
TOTAL
5,879.53
Add 1 % Water charges on “W”
58.80
TOTAL
5,938.33
Add GST on “X” (multiplying factor 0.2127)
1,263.08
TOTAL
7,201.41
Add 15% CPOH on “Y”
1,080.21
TOTAL
8,281.62
Add Cess @ 1% on “Z”
82.82
Cost of 1 cum.
8,364.44
Say
8,364.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 166. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.