Skip to main content
R/DAR 2023

Extra for addition of synthetic Polyester triangular fibre of length 12mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40 in cement concrete/RCC/Flooring/water retaining structures by using 125gms of synthetic Polyester triangular fibre for 50 Kg cement used as per directions of Engineer-in-Charge

Item number
4.18
Analysis basis
per bag
Priced inputs
1
Derived rate
₹70.35/ PER BAG
D-01/RATE ANALYSISITEM 4.18

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.18 (Extra for addition of synthetic Polyester triangular fibre of length 12mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40 in cement concrete/RCC/Flooring/water retaining structures by using 125gms of synthetic Polyester triangular fibre for 50 Kg cement used as per directions of Engineer-in-Charge) is derived from 1 priced inputs for per bag and works out to ₹70.35 per per bag after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • used in concrete
ANALYSIS OF RATES · ITEM 4.18DETAIL OF COST FOR PER BAG OF 50 KG OF CEMENT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8732MATSynthetic polyester triangular fibre of length 12mm, effective dia 10-40 microns and specific gravity of 1.34 to 1.40Synthetic ployster triangular fibre of length 12 mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40kg0.125395.5049.44
BUILD-UP TO RATE
TOTAL
49.44
Add 1 % Water charges on “W”
+0.49
TOTAL
49.93
Add GST on “X” (multiplying factor 0.2127)
+10.62
TOTAL
60.55
Add 15% CPOH on “Y”
+9.08
TOTAL
69.63
Add Cess @ 1% on “Z”
+0.70
Cost per bag of 50 kg of cement
70.33
SAY
₹70.35
D-02/SOURCEPRINTED PAGE 190
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
190

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 190. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.