CPWD Analysis of Rates · Concrete Work
Extra for addition of synthetic Polyester triangular fibre of length 12mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40 in cement concrete/RCC/Flooring/water retaining structures by using 125gms of synthetic Polyester triangular fibre for 50 Kg cement used as per directions of Engineer-in-Charge
- Item number
- 4.18
- Analysis basis
- Detail of cost for per bag of 50 kg of cement
- Priced inputs
- 1
- Derived rate
- ₹70.35 / per bag
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.18 — Extra for addition of synthetic Polyester triangular fibre of length 12mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40 in cement concrete/RCC/Flooring/water retaining structures by using 125gms of synthetic Polyester triangular fibre for 50 Kg cement used as per directions of Engineer-in-Charge — is derived from 1 priced inputs for per bag and works out to ₹70.35 per per bag after water charges, GST, CPOH and cess. The full build-up is below.
- used in concrete
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8732 | Synthetic polyester triangular fibre of length 12mm, effective dia 10-40 microns and specific gravity of 1.34 to 1.40Synthetic ployster triangular fibre of length 12 mm, effective diameter 10-40 microns and specific gravity of 1.34 to 1.40Material | kg | 0.125 | 395.50 | 49.44 |
- TOTAL
- 49.44
- Add 1 % Water charges on “W”
- 0.49
- TOTAL
- 49.93
- Add GST on “X” (multiplying factor 0.2127)
- 10.62
- TOTAL
- 60.55
- Add 15% CPOH on “Y”
- 9.08
- TOTAL
- 69.63
- Add Cess @ 1% on “Z”
- 0.70
- Cost per bag of 50 kg of cement
- 70.33
- Say
- 70.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 190. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.