CPWD Analysis of Rates · Concrete Work
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level
1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources)
- Item number
- 4.1.5
- Analysis basis
- Details of cost for 1 cum.
- Priced inputs
- 10
- Derived rate
- ₹7,294.70 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.5 — Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) — is derived from 10 priced inputs for 1 cum and works out to ₹7,294.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.7 | 1,425.00 | 997.50 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.24 | 1,400.00 | 336.00 |
| 0982 | Coarse sand (zone III)Material | cum | 0.47 | 1,450.00 | 681.50 |
| 0367 | Portland Cement(0.15674 cum)Portland Cement (OPC-43 Grade)Material | tonne | 0.22 | 5,156.00 | 1,134.32 |
| 0155 | Mason (average)Labour | day | 0.1 | 857.00 | 85.70 |
| 0114 | BeldarLabour | day | 1.63 | 736.00 | 1,199.68 |
| 0101 | BhistiLabour | day | 0.7 | 816.00 | 571.20 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with HopperMachinery | day | 0.07 | 900.00 | 63.00 |
| 0012 | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm)Machinery | day | 0.07 | 400.00 | 28.00 |
| 9999 | SundriesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 5,127.59
- Add 1 % Water charges on “W”
- 51.28
- TOTAL
- 5,178.87
- Add GST on “X” (multiplying factor 0.2127)
- 1,101.55
- TOTAL
- 6,280.42
- Add 15% CPOH on “Y”
- 942.06
- TOTAL
- 7,222.48
- Add Cess @ 1% on “Z”
- 72.22
- Cost of 1 cum.
- 7,294.70
- Say
- 7,294.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 154. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works