Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level
- Item number
- 4.1.4
- Analysis basis
- 1 cum
- Priced inputs
- 11
- Derived rate
- ₹7,780.30/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.4 (Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 40 mm nominal size derived from natural sources)) is derived from 11 priced inputs for 1 cum and works out to ₹7,780.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- 0.56 - (7.5% for voids i.e.) 0.04 = 0.52 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0293 | MAT | Stone Aggregate (Single size) : 40 mm nominal size,Stone Aggregate (Single size) : 40 mm nominal size | cum | 0.52 | 1,400.00 | 728.00 |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.22 | 1,425.00 | 313.50 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.11 | 1,400.00 | 154.00 |
| 0982 | MAT | Coarse sand (zone III) | cum | 0.445 | 1,450.00 | 645.25 |
| 0367 | MAT | Portland Cement (0.2225 cum)Portland Cement (OPC-43 Grade) | tonne | 0.32 | 5,156.00 | 1,649.92 |
| 0155 | LAB | Mason (average) | day | 0.1 | 857.00 | 85.70 |
| 0114 | LAB | Beldar | day | 1.63 | 736.00 | 1,199.68 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 5,468.94
- Add 1 % Water charges on “W”
- +54.69
- TOTAL
- 5,523.63
- Add GST on “X” (multiplying factor 0.2127)
- +1,174.88
- TOTAL
- 6,698.51
- Add 15% CPOH on “Y”
- +1,004.78
- TOTAL
- 7,703.29
- Add Cess @ 1% on “Z”
- +77.03
- Cost of 1 cum.
- 7,780.32
- SAY
- ₹7,780.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 153
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 153. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.