Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level
- Item number
- 4.1.13
- Analysis basis
- 1 cum
- Priced inputs
- 12
- Derived rate
- ₹6,311.95/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.13 (Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2½:4:11 (1 ordinary portland cement : 2½ fly ash : 4 coarse sand(zone-III) derived from natural sources : 11 graded stone aggregate 40 mm nominal size derived from natural sources)) is derived from 12 priced inputs for 1 cum and works out to ₹6,311.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- (0.70 cum-7.5% for voids i.e. 0.05 = 0.65 cum)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0293 | MAT | Stone Aggregate (Single size) : 40 mm nominal size | cum | 0.65 | 1,400.00 | 910.00 |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.24 | 1,425.00 | 342.00 |
| 0982 | MAT | Coarse sand (zone III) | cum | 0.34 | 1,450.00 | 493.00 |
| 1980 | MAT | FlyashFly ash | cum | 0.21 | 12.00 | 2.52 |
| 2262 | MAT | Carriage of Flyash | cum | 0.21 | 185.55 | 38.97 |
| 0367 | MAT | Portland CementPortland Cement (OPC-43 Grade) | tonne | 0.13 | 5,156.00 | 670.28 |
| 0155 | LAB | Mason (average) | day | 0.1 | 857.00 | 85.70 |
| 0114 | LAB | Beldar | day | 1.63 | 736.00 | 1,199.68 |
| 0101 | LAB | Bhisti | day | 0.7 | 816.00 | 571.20 |
| 0002 | MACH | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper | day | 0.07 | 900.00 | 63.00 |
| 0012 | MACH | Vibrator(Needle type 40mm)Vibrator (Needle type 40 mm) | day | 0.07 | 400.00 | 28.00 |
| 9999 | MAT | Sundries | L.S. | 14.3 | 2.27 | 32.46 |
- TOTAL
- 4,436.81
- Add 1 % Water charges on “W”
- +44.37
- TOTAL
- 4,481.18
- Add GST on “X” (multiplying factor 0.2127)
- +953.15
- TOTAL
- 5,434.33
- Add 15% CPOH on “Y”
- +815.15
- TOTAL
- 6,249.48
- Add Cess @ 1% on “Z”
- +62.49
- Cost of one cum.
- 6,311.97
- SAY
- ₹6,311.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 161
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 161. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.