Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level

1:2½:4:11 (1 ordinary portland cement : 2½ fly ash : 4 coarse sand(zone-III) derived from natural sources : 11 graded stone aggregate 40 mm nominal size derived from natural sources)
Item number
4.1.13
Analysis basis
1 cum
Priced inputs
12
Derived rate
₹6,311.95/ CUM
D-01/RATE ANALYSISITEM 4.1.13

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.13 (Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2½:4:11 (1 ordinary portland cement : 2½ fly ash : 4 coarse sand(zone-III) derived from natural sources : 11 graded stone aggregate 40 mm nominal size derived from natural sources)) is derived from 12 priced inputs for 1 cum and works out to ₹6,311.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (0.70 cum-7.5% for voids i.e. 0.05 = 0.65 cum)
ANALYSIS OF RATES · ITEM 4.1.13DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0293MATStone Aggregate (Single size) : 40 mm nominal sizecum0.651,400.00910.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.241,425.00342.00
0982MATCoarse sand (zone III)cum0.341,450.00493.00
1980MATFlyashFly ashcum0.2112.002.52
2262MATCarriage of Flyashcum0.21185.5538.97
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.135,156.00670.28
0155LABMason (average)day0.1857.0085.70
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundriesL.S.14.32.2732.46
BUILD-UP TO RATE
TOTAL
4,436.81
Add 1 % Water charges on “W”
+44.37
TOTAL
4,481.18
Add GST on “X” (multiplying factor 0.2127)
+953.15
TOTAL
5,434.33
Add 15% CPOH on “Y”
+815.15
TOTAL
6,249.48
Add Cess @ 1% on “Z”
+62.49
Cost of one cum.
6,311.97
SAY
₹6,311.95
D-02/SOURCEPRINTED PAGE 161
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
161

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 161. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.