Skip to main content
R/DAR 2023

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level

1:2:3½:9 (1 ordinary portland cement : 2 Fly ash : 3½ manufactured sand derived from Recycled Concrete Aggregate (RCA) : 9 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) )
Item number
4.1.12A
Analysis basis
1 cum
Priced inputs
12
Derived rate
₹5,130.65/ CUM
D-01/RATE ANALYSISITEM 4.1.12A

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 4.1.12A (Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:3½:9 (1 ordinary portland cement : 2 Fly ash : 3½ manufactured sand derived from Recycled Concrete Aggregate (RCA) : 9 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) )) is derived from 12 priced inputs for 1 cum and works out to ₹5,130.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 4.1.12ADETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0282MATRecycled Aggregate (RA) 40 mm nominal sizecum0.65390.00253.50
0283MATRecycled Aggregate (RA) 20 mm nominal sizecum0.24420.00100.80
0278MATManufactured sand derived from Recycled Concrete Aggregate (RCA)cum0.37957.00354.09
1980MATFlyashFly ashcum0.2112.002.52
2262MATCarriage of Flyashcum0.21185.5538.97
0367MATPortland CementPortland Cement (OPC-43 Grade)tonne0.175,156.00876.52
0155LABMason (average)day0.1857.0085.70
0114LABBeldarday1.63736.001,199.68
0101LABBhistiday0.7816.00571.20
0002MACHHire charges of Concrete Mixer 0.25 to 0.40 cum with hooperHire charges of Concrete Mixer 0.25 to 0.40 cum with Hopperday0.07900.0063.00
0012MACHVibrator(Needle type 40mm)Vibrator (Needle type 40 mm)day0.07400.0028.00
9999MATSundriesL.S.14.32.2732.46
BUILD-UP TO RATE
TOTAL
3,606.44
Add 1 % Water charges on “W”
+36.06
TOTAL
3,642.50
Add GST on “X” (multiplying factor 0.2127)
+774.76
TOTAL
4,417.26
Add 15% CPOH on “Y”
+662.59
TOTAL
5,079.85
Add Cess @ 1% on “Z”
+50.80
Cost of 1 cum.
5,130.65
SAY
₹5,130.65
D-02/SOURCEPRINTED PAGE 160
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
160

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 160. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCONCRETE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.