Providing and fixing in wall lining flat pressed three layer (medium density) particle board or graded wood Pre-laminated one side decorative lamination and other side balancing lamination Grade I, Type II, IS : 12823 marked, including priming coat on unexposed arrangement and screws etc. complete

18 mm thick
Item number
8.26.2
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹1,492.80/ SQM
D-01/RATE ANALYSISITEM 8.26.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.26.2 (Providing and fixing in wall lining flat pressed three layer (medium density) particle board or graded wood Pre-laminated one side decorative lamination and other side balancing lamination Grade I, Type II, IS : 12823 marked, including priming coat on unexposed arrangement and screws etc. complete : 18 mm thick) is derived from 7 priced inputs for 10 sqm and works out to ₹1,492.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Particle board (three layer medium density) 18
  • mm thick = 10 sqm.
  • Total = 11 sqm.
  • Priming coat
  • Add wastage @ 10% = 1 sqm.
ANALYSIS OF RATES · ITEM 8.26.2DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7478MATPrelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 18 mm thickPrelaminated flat pressed three layer or graded wood particle board with one side decorative and other side balancing lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 18 mm thicksqm11590.006,490.00
9977MATCarriage of particle boardL.S.13.522.2730.69
9999MATSundries and screwsL.S.26.912.2761.09
SUBRate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1sqm1070.35703.50
0112LABCarpenter 2nd classday1.28816.001,044.48
0114LABBeldarday1.43736.001,052.48
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each5524.001,320.00
BUILD-UP TO RATE
TOTAL
10,702.24
Add 1 % Water charges on “W-A”
+99.99
TOTAL
10,802.23
Add GST on “X-A” (multiplying factor 0.2127)
+2,148.00
TOTAL
12,950.23
Add 15% CPOH on “Y-A”
+1,837.01
TOTAL
14,787.24
Add Cess @ 1% on “Z-A”
+140.84
Cost of 10 sqm.
14,928.08
Cost of 1 sqm.
1,492.81
SAY
₹1,492.80
D-02/SOURCEPRINTED PAGE 425
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
425

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 425. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.