CPWD Analysis of Rates · Cladding Work
Providing and fixing in wall lining flat pressed three layer (medium density) particle board or graded wood Pre-laminated one side decorative lamination and other side balancing lamination Grade I, Type II, IS : 12823 marked, including priming coat on unexposed arrangement and screws etc. complete
18 mm thick
- Item number
- 8.26.2
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 7
- Derived rate
- ₹1,492.80 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.26.2 — Providing and fixing in wall lining flat pressed three layer (medium density) particle board or graded wood Pre-laminated one side decorative lamination and other side balancing lamination Grade I, Type II, IS : 12823 marked, including priming coat on unexposed arrangement and screws etc. complete : 18 mm thick — is derived from 7 priced inputs for 10 sqm and works out to ₹1,492.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Particle board (three layer medium density) 18
- mm thick = 10 sqm.
- Total = 11 sqm.
- Priming coat
- Add wastage @ 10% = 1 sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7478 | Prelaminated particle board with one side decorative and other side balancing lamination, flat pressed 3 layer & graded (medium density) Grade I, Type II conforming to IS : 12823 (exterior grade) 18 mm thickPrelaminated flat pressed three layer or graded wood particle board with one side decorative and other side balancing lamination, (medium density) Grade I, Type II conforming and marked to IS : 12823 (exterior grade) 18 mm thickMaterial | sqm | 11 | 590.00 | 6,490.00 |
| 9977 | Carriage of particle boardMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Sundries and screwsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysis | sqm | 10 | 70.35 | 703.50 | |
| 0112 | Carpenter 2nd classLabour | day | 1.28 | 816.00 | 1,044.48 |
| 0114 | BeldarLabour | day | 1.43 | 736.00 | 1,052.48 |
| 7048 | Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)Material | each | 55 | 24.00 | 1,320.00 |
- TOTAL
- 10,702.24
- Add 1 % Water charges on “W-A”
- 99.99
- TOTAL
- 10,802.23
- Add GST on “X-A” (multiplying factor 0.2127)
- 2,148.00
- TOTAL
- 12,950.23
- Add 15% CPOH on “Y-A”
- 1,837.01
- TOTAL
- 14,787.24
- Add Cess @ 1% on “Z-A”
- 140.84
- Cost of 10 sqm.
- 14,928.08
- Cost of 1 sqm.
- 1,492.81
- Say
- 1,492.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 425. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.