Providing and fixing adjustable stainless steel cramps of approved quality, required shape and size, adjustable with stainless steel nuts, bolts and washer (total weight not less than 260 gms), for dry stone cladding fixed on frame work at suitable location, including making necessary recesses in stone slab, drilling required holes etc complete as per direction of the Engineer-incharge

Item number
8.22
Analysis basis
10 Nos
Priced inputs
6
Derived rate
₹437.00/ NOS
D-01/RATE ANALYSISITEM 8.22

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.22 (Providing and fixing adjustable stainless steel cramps of approved quality, required shape and size, adjustable with stainless steel nuts, bolts and washer (total weight not less than 260 gms), for dry stone cladding fixed on frame work at suitable location, including making necessary recesses in stone slab, drilling required holes etc complete as per direction of the Engineer-incharge) is derived from 6 priced inputs for 10 Nos and works out to ₹437.00 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • For making holes, recesses etc. and fixing of
  • stainless steel cramps.
ANALYSIS OF RATES · ITEM 8.22DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8698MATStainless steel cramps(weight 260 grams) with nuts, bolts and washer for dry stone claddingeach10127.001,270.00
0103LABBlacksmith 2nd classday0.1816.0081.60
0124LABMason 2nd classMason 2nd classday1816.00816.00
0114LABBeldarday1.1736.00809.60
9999MATScaffolding, hire charges of drill machine etc.L.S.20.82.2747.22
9999MATSundriesL.S.20.82.2747.22
BUILD-UP TO RATE
TOTAL
3,071.64
Add 1 % Water charges on “W”
+30.72
TOTAL
3,102.36
Add GST on “X” (multiplying factor 0.2127)
+659.87
TOTAL
3,762.23
Add 15% CPOH on “Y”
+564.33
TOTAL
4,326.56
Add Cess @ 1% on “Z”
+43.27
Cost for 10 Nos.
4,369.83
Cost for 1 Nos.
436.98
SAY
₹437.00
D-02/SOURCEPRINTED PAGE 419
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
419

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 419. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.