Providing and fixing adjustable stainless steel cramps of approved quality, required shape and size, adjustable with stainless steel nuts, bolts and washer (total weight not less than 260 gms), for dry stone cladding fixed on frame work at suitable location, including making necessary recesses in stone slab, drilling required holes etc complete as per direction of the Engineer-incharge

Item number
8.22
Analysis basis
Details of cost for 10 Nos.
Priced inputs
6
Derived rate
437.00 / Nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.22 Providing and fixing adjustable stainless steel cramps of approved quality, required shape and size, adjustable with stainless steel nuts, bolts and washer (total weight not less than 260 gms), for dry stone cladding fixed on frame work at suitable location, including making necessary recesses in stone slab, drilling required holes etc complete as per direction of the Engineer-incharge — is derived from 6 priced inputs for 10 Nos and works out to ₹437.00 each after water charges, GST, CPOH and cess. The full build-up is below.

  • For making holes, recesses etc. and fixing of
  • stainless steel cramps.
CodeInputUnitQuantityRate (INR)Amount (INR)
8698Stainless steel cramps(weight 260 grams) with nuts, bolts and washer for dry stone claddingMaterialeach10127.001,270.00
0103Blacksmith 2nd classLabourday0.1816.0081.60
0124Mason 2nd classMason 2nd classLabourday1816.00816.00
0114BeldarLabourday1.1736.00809.60
9999Scaffolding, hire charges of drill machine etc.MaterialL.S.20.82.2747.22
9999SundriesMaterialL.S.20.82.2747.22
TOTAL
3,071.64
Add 1 % Water charges on “W”
30.72
TOTAL
3,102.36
Add GST on “X” (multiplying factor 0.2127)
659.87
TOTAL
3,762.23
Add 15% CPOH on “Y”
564.33
TOTAL
4,326.56
Add Cess @ 1% on “Z”
43.27
Cost for 10 Nos.
4,369.83
Cost for 1 Nos.
436.98
Say
437.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 419. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works