CPWD Analysis of Rates · Cladding Work
Area of slab over 0.50 sqm
- Item number
- 8.2.1.2
- Analysis basis
- Details of cost for 1.00 sqm.
- Priced inputs
- 7
- Derived rate
- ₹3,078.40 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.2.1.2 — Area of slab over 0.50 sqm — is derived from 7 priced inputs for 1.00 sqm and works out to ₹3,078.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Mirror polished Abu plain white = 1.00 sqm.+
- Wastage 5% (0.05sqm.)= 1.05 sqm
- 20mm thick Cement mortar 1 : 4 (1 cement : 4
- coarse sand)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7453 | Raj nagar plain white marble (table rubbed and polished) 18 mm thick (slab area more than 0.50 sqm)Material | sqm | 1.05 | 690.00 | 724.50 |
| Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9Sub-analysis | cum | 0.024 | 4,211.70 | 101.08 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.72 | 897.00 | 645.84 |
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
| 0115 | CoolieLabour | day | 0.3 | 736.00 | 220.80 |
| 9999 | Moulding and edge polishingMaterial | L.S. | 78 | 2.27 | 177.06 |
| 9999 | Sundries apoxy resin & cutting machine etc.Material | L.S. | 32.5 | 2.27 | 73.78 |
- TOTAL
- 2,163.86
- Add 1 % Water charges on “W”
- 21.64
- TOTAL
- 2,185.50
- Add GST on “X” (multiplying factor 0.2127)
- 464.86
- TOTAL
- 2,650.36
- Add 15% CPOH on “Y”
- 397.55
- TOTAL
- 3,047.91
- Add Cess @ 1% on “Z”
- 30.48
- Cost for 1.00 sqm.
- 3,078.39
- Say
- 3,078.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 385. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works