Area of slab over 0.50 sqm
- Item number
- 8.2.1.2
- Analysis basis
- 1.00 sqm
- Priced inputs
- 7
- Derived rate
- ₹3,078.40/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.2.1.2 (Area of slab over 0.50 sqm) is derived from 7 priced inputs for 1.00 sqm and works out to ₹3,078.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Mirror polished Abu plain white = 1.00 sqm.+
- Wastage 5% (0.05sqm.)= 1.05 sqm
- 20mm thick Cement mortar 1 : 4 (1 cement : 4
- coarse sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7453 | MAT | Raj nagar plain white marble (table rubbed and polished) 18 mm thick (slab area more than 0.50 sqm) | sqm | 1.05 | 690.00 | 724.50 |
| SUB | Rate as per Item Number 3.9 of SH: MortarsRate as per item 3.9 | cum | 0.024 | 4,211.70 | 101.08 | |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.72 | 897.00 | 645.84 |
| 0114 | LAB | Beldar | day | 0.3 | 736.00 | 220.80 |
| 0115 | LAB | Coolie | day | 0.3 | 736.00 | 220.80 |
| 9999 | MAT | Moulding and edge polishing | L.S. | 78 | 2.27 | 177.06 |
| 9999 | MAT | Sundries apoxy resin & cutting machine etc. | L.S. | 32.5 | 2.27 | 73.78 |
- TOTAL
- 2,163.86
- Add 1 % Water charges on “W”
- +21.64
- TOTAL
- 2,185.50
- Add GST on “X” (multiplying factor 0.2127)
- +464.86
- TOTAL
- 2,650.36
- Add 15% CPOH on “Y”
- +397.55
- TOTAL
- 3,047.91
- Add Cess @ 1% on “Z”
- +30.48
- Cost for 1.00 sqm.
- 3,078.39
- SAY
- ₹3,078.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 385
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 385. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.