Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required

Item number
8.15
Analysis basis
one cramp
Priced inputs
4
Derived rate
₹714.40/ ONE CRAMP
D-01/RATE ANALYSISITEM 8.15

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.15 (Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required) is derived from 4 priced inputs for one cramp and works out to ₹714.40 per one cramp after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Stainless steel cramp
  • 10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^5
  • 10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^5
  • = 13.3 x 10^5
  • = 1.4 x 10^5
  • = 11.9 x 10^5 x 7850 = 0.934 kg
  • Total = 0.981 kg.
  • Cement mortar 1:2 (1 cement : 2 coarse sand)
  • less hole 10 x 0.024 x 0.010 x 0.006
  • Add wastage @ 5% = 0.047kg.
ANALYSIS OF RATES · ITEM 8.15DETAILS OF COST FOR ONE CRAMP OF 0.934KG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7339MATStainless steel crampgram0.981313.00307.05
9977MATCARRIAGEL.S.3.92.278.85
SUBRate as per Item Number 3.7 of SH: MortarsRate as per item 3.7cum0.0015,584.505.58
9999MATLabour for fixing in positionL.S.652.27147.55
BUILD-UP TO RATE
TOTAL
469.03
Add 1 % Water charges on “W”
+4.69
TOTAL
473.72
Add GST on “X” (multiplying factor 0.2127)
+100.76
TOTAL
574.48
Add 15% CPOH on “Y”
+86.17
TOTAL
660.65
Add Cess @ 1% on “Z”
+6.61
Cost for 0.934 kg.
667.26
Cost per kg
714.41
SAY
₹714.40
D-02/SOURCEPRINTED PAGE 413
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
413

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 413. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.