CPWD Analysis of Rates · Cladding Work

Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required

Item number
8.15
Analysis basis
Details of cost for one cramp of 0.934kg
Priced inputs
4
Derived rate
714.40 / one cramp

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.15 Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required — is derived from 4 priced inputs for one cramp and works out to ₹714.40 per one cramp after water charges, GST, CPOH and cess. The full build-up is below.

  • Stainless steel cramp
  • 10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^5
  • 10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^5
  • = 13.3 x 10^5
  • = 1.4 x 10^5
  • = 11.9 x 10^5 x 7850 = 0.934 kg
  • Total = 0.981 kg.
  • Cement mortar 1:2 (1 cement : 2 coarse sand)
  • less hole 10 x 0.024 x 0.010 x 0.006
  • Add wastage @ 5% = 0.047kg.
CodeInputUnitQuantityRate (INR)Amount (INR)
7339Stainless steel crampMaterialgram0.981313.00307.05
9977CARRIAGEMaterialL.S.3.92.278.85
Rate as per Item Number 3.7 of SH: MortarsRate as per item 3.7Sub-analysiscum0.0015,584.505.58
9999Labour for fixing in positionMaterialL.S.652.27147.55
TOTAL
469.03
Add 1 % Water charges on “W”
4.69
TOTAL
473.72
Add GST on “X” (multiplying factor 0.2127)
100.76
TOTAL
574.48
Add 15% CPOH on “Y”
86.17
TOTAL
660.65
Add Cess @ 1% on “Z”
6.61
Cost for 0.934 kg.
667.26
Cost per kg
714.41
Say
714.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 413. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works