Providing and fixing machine cut, mirror/ eggshell polished , Marble stone work for wall lining (veneer work) including dado, skirting, risers of steps etc., in required design and pattern wherever required, stones of different finished surface texture, on 12 mm (average) thick cement mortar 1:3 (1 cement : 3 coarse sand) laid and jointed with white cement slurry @ 3.3 kg/sqm including pointing with white cement slurry admixed with pigment of matching shade, including rubbing, curing, polishing etc. all complete as per Architectural drawings, and as directed by the Engineer-in-Charge
- Item number
- 8.11.1
- Analysis basis
- 50 sqm
- Priced inputs
- 12
- Derived rate
- ₹10,414.80/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.11.1 (Providing and fixing machine cut, mirror/ eggshell polished , Marble stone work for wall lining (veneer work) including dado, skirting, risers of steps etc., in required design and pattern wherever required, stones of different finished surface texture, on 12 mm (average) thick cement mortar 1:3 (1 cement : 3 coarse sand) laid and jointed with white cement slurry @ 3.3 kg/sqm including pointing with white cement slurry admixed with pigment of matching shade, including rubbing, curing, polishing etc. all complete as per Architectural drawings, and as directed by the Engineer-in-Charge 18 mm thick Italian Marble stone slab,Perlato, Rosso verona, Fire Red or Dark Emperadore etc) is derived from 12 priced inputs for 50 sqm and works out to ₹10,414.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work= 50 sqm+Add for wastage @
- 20%=10 sqm. Total = 60 sqm
- LABOUR :
- FOR fixing
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1240 | MAT | 18 mm thick Italian Marble stone slab, Perlato (slab area up to 0.5 sqm)18 mm thick Italian Marble stone slab, Perlato (slab area up to 0.5 sqm). | sqm | 60 | 3,200.00 | 1,92,000.00 |
| SUB | Rate as per Item No.3.8 of SH: MORTARSRate as per item 3.8 | cum | 0.8 | 4,881.95 | 3,905.56 | |
| 0368 | MAT | White Cement Slurry @ 3.3kg/sqmWhite Cement | tonne | 0.165 | 10,500.00 | 1,732.50 |
| 9999 | MAT | Mortar for pointing in white cement | L.S. | 2,535 | 2.27 | 5,754.45 |
| 0126 | LAB | Mason (for ornamental stone work) 1st class | day | 33.5 | 897.00 | 30,049.50 |
| 0100 | LAB | Bandhani | day | 33.5 | 816.00 | 27,336.00 |
| 0114 | LAB | Beldar | day | 33.5 | 736.00 | 24,656.00 |
| 0115 | LAB | Coolie | day | 33.5 | 736.00 | 24,656.00 |
| 0101 | LAB | Bhisti | day | 33.5 | 816.00 | 27,336.00 |
| 0128 | LAB | Mate | day | 16.5 | 816.00 | 13,464.00 |
| 0102 | LAB | Blacksmith 1st class | day | 13.5 | 897.00 | 12,109.50 |
| 9999 | MAT | Scaffolding | L.S. | 1,339 | 2.27 | 3,039.53 |
- TOTAL
- 3,66,039.04
- Add 1 % Water charges on “W”
- +3,660.39
- TOTAL
- 3,69,699.43
- Add GST on “X” (multiplying factor 0.2127)
- +78,635.07
- TOTAL
- 4,48,334.50
- Add 15% CPOH on “Y”
- +67,250.18
- TOTAL
- 5,15,584.68
- Add Cess @ 1% on “Z”
- +5,155.85
- Cost of 50 sqm
- 5,20,740.53
- Cost of 1 sqm
- 10,414.81
- SAY
- ₹10,414.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 395
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 395. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.