Skip to main content

CPWD Analysis of Rates · Cladding Work

Providing and fixing machine cut, mirror/ eggshell polished , Marble stone work for wall lining (veneer work) including dado, skirting, risers of steps etc., in required design and pattern wherever required, stones of different finished surface texture, on 12 mm (average) thick cement mortar 1:3 (1 cement : 3 coarse sand) laid and jointed with white cement slurry @ 3.3 kg/sqm including pointing with white cement slurry admixed with pigment of matching shade, including rubbing, curing, polishing etc. all complete as per Architectural drawings, and as directed by the Engineer-in-Charge

18 mm thick Italian Marble stone slab,Perlato, Rosso verona, Fire Red or Dark Emperadore etc

Item number
8.11.1
Analysis basis
Details of cost for 50 sqm
Priced inputs
12
Derived rate
10,414.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.11.1 Providing and fixing machine cut, mirror/ eggshell polished , Marble stone work for wall lining (veneer work) including dado, skirting, risers of steps etc., in required design and pattern wherever required, stones of different finished surface texture, on 12 mm (average) thick cement mortar 1:3 (1 cement : 3 coarse sand) laid and jointed with white cement slurry @ 3.3 kg/sqm including pointing with white cement slurry admixed with pigment of matching shade, including rubbing, curing, polishing etc. all complete as per Architectural drawings, and as directed by the Engineer-in-Charge 18 mm thick Italian Marble stone slab,Perlato, Rosso verona, Fire Red or Dark Emperadore etc — is derived from 12 priced inputs for 50 sqm and works out to ₹10,414.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Finished work= 50 sqm+Add for wastage @
  • 20%=10 sqm. Total = 60 sqm
  • LABOUR :
  • FOR fixing
CodeInputUnitQuantityRate (INR)Amount (INR)
124018 mm thick Italian Marble stone slab, Perlato (slab area up to 0.5 sqm)18 mm thick Italian Marble stone slab, Perlato (slab area up to 0.5 sqm).Materialsqm603,200.001,92,000.00
Rate as per Item No.3.8 of SH: MORTARSRate as per item 3.8Sub-analysiscum0.84,881.953,905.56
0368White Cement Slurry @ 3.3kg/sqmWhite CementMaterialtonne0.16510,500.001,732.50
9999Mortar for pointing in white cementMaterialL.S.2,5352.275,754.45
0126Mason (for ornamental stone work) 1st classLabourday33.5897.0030,049.50
0100BandhaniLabourday33.5816.0027,336.00
0114BeldarLabourday33.5736.0024,656.00
0115CoolieLabourday33.5736.0024,656.00
0101BhistiLabourday33.5816.0027,336.00
0128MateLabourday16.5816.0013,464.00
0102Blacksmith 1st classLabourday13.5897.0012,109.50
9999ScaffoldingMaterialL.S.1,3392.273,039.53
TOTAL
3,66,039.04
Add 1 % Water charges on “W”
3,660.39
TOTAL
3,69,699.43
Add GST on “X” (multiplying factor 0.2127)
78,635.07
TOTAL
4,48,334.50
Add 15% CPOH on “Y”
67,250.18
TOTAL
5,15,584.68
Add Cess @ 1% on “Z”
5,155.85
Cost of 50 sqm
5,20,740.53
Cost of 1 sqm
10,414.81
Say
10,414.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 395. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works