Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately) Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble
Area of slab over 0.50 sqm
- Item number
- 8.1.1.2
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 11
- Derived rate
- ₹5,938.00 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.1.1.2 — Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately) Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble Area of slab over 0.50 sqm — is derived from 11 priced inputs for 10 sqm and works out to ₹5,938.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 sqm. Add for wastage @
- 20% = 2 sqm. Total = 12 sqm.
- Cement mortar 1:3 (1 cement : 3 coarse sand)
- White cement mortar 1:2 (1 white cement : 2
- marble dust)
- For fixing
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7453 | Raj nagar plain white marble (table rubbed and polished) 18 mm thick (slab area more than 0.50 sqm)Material | sqm | 12 | 690.00 | 8,280.00 |
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.144 | 4,881.95 | 703.00 | |
| Rate as per Item Number 3.15 of SH: MortarsRate as per item 3.15Sub-analysis | cum | 0.025 | 8,961.90 | 224.05 | |
| 0126 | Mason (for ornamental stone work) 1st classLabour | day | 6.7 | 897.00 | 6,009.90 |
| 0100 | BandhaniLabour | day | 6.7 | 816.00 | 5,467.20 |
| 0114 | BeldarLabour | day | 6.7 | 736.00 | 4,931.20 |
| 0115 | CoolieLabour | day | 6.7 | 736.00 | 4,931.20 |
| 0101 | BhistiLabour | day | 6.7 | 816.00 | 5,467.20 |
| 0128 | MateLabour | day | 3.3 | 816.00 | 2,692.80 |
| 0102 | Blacksmith 1st classLabour | day | 2.7 | 897.00 | 2,421.90 |
| 9999 | ScaffoldingMaterial | L.S. | 269.1 | 2.27 | 610.86 |
- TOTAL
- 41,739.31
- Add 1 % Water charges on “W”
- 417.39
- TOTAL
- 42,156.70
- Add GST on “X” (multiplying factor 0.2127)
- 8,966.73
- TOTAL
- 51,123.43
- Add 15% CPOH on “Y”
- 7,668.51
- TOTAL
- 58,791.94
- Add Cess @ 1% on “Z”
- 587.92
- Cost for 10 sqm
- 59,379.86
- Cost for one sqm
- 5,937.99
- Say
- 5,938.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 383. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works