Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately) Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble
- Item number
- 8.1.1.1
- Analysis basis
- 5 sqm
- Priced inputs
- 11
- Derived rate
- ₹5,742.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 8.1.1.1 (Marble work gang saw cut (polished and machine cut) of thickness 18 mm for wall lining (veneer work), backing filled with a grout of average 12 mm thick in cement mortar 1:3 (1 cement : 3 coarse sand), including pointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture of pigment to match the marble shade (To be secured to the backing by means of cramps, which shall be paid for separately) Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble Area of slab upto 0.50 sqm) is derived from 11 priced inputs for 5 sqm and works out to ₹5,742.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 5sqm. Add for wastage @ 20%
- = 1 sqm. Total = 6 sqm.
- Cement mortar 1:3 (1 cement : 3 coarse sand)
- White cement mortar 1:2 (1 white cement : 2
- marble dust)
- For fixing
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7452 | MAT | Raj nagar plain white marble (table rubbed and polished) 18 mm thick (slab area upto 0.50 sqm) | sqm | 6 | 570.00 | 3,420.00 |
| SUB | Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8 | cum | 0.08 | 4,881.95 | 390.56 | |
| SUB | Rate as per Item Number 3.15 of SH: MortarsRate as per item 3.15 | cum | 0.012 | 8,961.90 | 107.54 | |
| 0126 | LAB | Mason (for ornamental stone work) 1st class | day | 3.35 | 897.00 | 3,004.95 |
| 0100 | LAB | Bandhani | day | 3.35 | 816.00 | 2,733.60 |
| 0114 | LAB | Beldar | day | 3.35 | 736.00 | 2,465.60 |
| 0115 | LAB | Coolie | day | 3.35 | 736.00 | 2,465.60 |
| 0101 | LAB | Bhisti | day | 3.35 | 816.00 | 2,733.60 |
| 0128 | LAB | Mate | day | 1.65 | 816.00 | 1,346.40 |
| 0102 | LAB | Blacksmith 1st class | day | 1.35 | 897.00 | 1,210.95 |
| 9999 | MAT | Scaffolding | L.S. | 133.9 | 2.27 | 303.95 |
- TOTAL
- 20,182.75
- Add 1 % Water charges on “W”
- +201.83
- TOTAL
- 20,384.58
- Add GST on “X” (multiplying factor 0.2127)
- +4,335.80
- TOTAL
- 24,720.38
- Add 15% CPOH on “Y”
- +3,708.06
- TOTAL
- 28,428.44
- Add Cess @ 1% on “Z”
- +284.28
- Cost for 5 sqm.
- 28,712.72
- Cost for one sqm.
- 5,742.54
- SAY
- ₹5,742.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 383
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 383. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.