Heavy materials where each piece or bundle, crate or case weighs more than one tonne and R.C.C., C.I. and concrete pipes above 500 mm dia
- Item number
- 1.4.3
- Analysis basis
- Details of cost of unloading wagon of 14 tonnes
- Priced inputs
- 3
- Derived rate
- ₹263.15/ TONNE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.4.3 (Heavy materials where each piece or bundle, crate or case weighs more than one tonne and R.C.C., C.I. and concrete pipes above 500 mm dia) is derived from 3 priced inputs and works out to ₹263.15 per tonne after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 3.25 | 736.00 | 2,392.00 |
| 9999 | MAT | Extra for fixing crane including labour involved | L.S. | 91.15 | 2.27 | 206.91 |
| 9999 | MAT | Sundries | L.S. | 7.4 | 2.27 | 16.80 |
- TOTAL
- 2,615.71
- Add GST on “X” (multiplying factor 0.2127)
- +556.36
- TOTAL
- 3,172.07
- Add 15% CPOH on “Y”
- +475.81
- TOTAL
- 3,647.88
- Add Cess @ 1% on “Z”
- +36.48
- Cost of 14 tonne
- 3,684.36
- Cost of 1 tonne
- 263.17
- SAY
- ₹263.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 89
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 89. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.