G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials

Item number
1.4.2
Analysis basis
Details of cost of unloading wagon of 14
Priced inputs
2
Derived rate
₹148.80/ TONNE
D-01/RATE ANALYSISITEM 1.4.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.4.2 (G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials) is derived from 2 priced inputs and works out to ₹148.80 per tonne after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • tonnes
ANALYSIS OF RATES · ITEM 1.4.2DETAILS OF COST OF UNLOADING WAGON OF 14
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday2736.001,472.00
9999MATSundriesL.S.3.12.277.04
BUILD-UP TO RATE
TOTAL
1,479.04
Add GST on “X” (multiplying factor 0.2127)
+314.59
TOTAL
1,793.63
Add 15% CPOH on “Y”
+269.04
TOTAL
2,062.67
Add Cess @ 1% on “Z”
+20.63
Cost of 14 tonne
2,083.30
Cost of 1 tonne
148.81
SAY
₹148.80
D-02/SOURCEPRINTED PAGE 89
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
89

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 89. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCARRIAGE OF MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.