CPWD Analysis of Rates · Carriage of Materials
G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials
- Item number
- 1.4.2
- Analysis basis
- Details of cost of unloading wagon of 14
- Priced inputs
- 2
- Derived rate
- ₹148.80 / tonne
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.4.2 — G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials — is derived from 2 priced inputs and works out to ₹148.80 per tonne after water charges, GST, CPOH and cess. The full build-up is below.
- tonnes
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 9999 | SundriesMaterial | L.S. | 3.1 | 2.27 | 7.04 |
- TOTAL
- 1,479.04
- Add GST on “X” (multiplying factor 0.2127)
- 314.59
- TOTAL
- 1,793.63
- Add 15% CPOH on “Y”
- 269.04
- TOTAL
- 2,062.67
- Add Cess @ 1% on “Z”
- 20.63
- Cost of 14 tonne
- 2,083.30
- Cost of 1 tonne
- 148.81
- Say
- 148.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 89. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works