G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials
- Item number
- 1.4.2
- Analysis basis
- Details of cost of unloading wagon of 14
- Priced inputs
- 2
- Derived rate
- ₹148.80/ TONNE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.4.2 (G.I., C.I., R.C.C. or C.C. pipes upto 500 mm dia and similar heavy materials) is derived from 2 priced inputs and works out to ₹148.80 per tonne after water charges, GST, CPOH and cess. The full build-up is below.
- tonnes
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 9999 | MAT | Sundries | L.S. | 3.1 | 2.27 | 7.04 |
- TOTAL
- 1,479.04
- Add GST on “X” (multiplying factor 0.2127)
- +314.59
- TOTAL
- 1,793.63
- Add 15% CPOH on “Y”
- +269.04
- TOTAL
- 2,062.67
- Add Cess @ 1% on “Z”
- +20.63
- Cost of 14 tonne
- 2,083.30
- Cost of 1 tonne
- 148.81
- SAY
- ₹148.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 89
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 89. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.