Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete

Item number
1.3
Priced inputs
2
Derived rate
₹169.40/ TONNE
D-01/RATE ANALYSISITEM 1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.3 (Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete) is derived from 2 priced inputs and works out to ₹169.40 per tonne after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details of 23 tonnes of cement
  • Sundries Add for sweeping the wagon,
ANALYSIS OF RATES · ITEM 1.3
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday3.75736.002,760.00
9999MATscreening the swept cement and filling the same in bagsL.S.2.622.275.95
BUILD-UP TO RATE
TOTAL
2,765.95
Add GST on “X” (multiplying factor 0.2127)
+588.32
TOTAL
3,354.27
Add 15% CPOH on “Y”
+503.14
TOTAL
3,857.41
Add Cess @ 1% on “Z”
+38.57
Cost of 23 tonne
3,895.98
Cost of 1 tonne
169.39
SAY
₹169.40
D-02/SOURCEPRINTED PAGE 114
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
114

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 114. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSCARRIAGE OF MATERIALS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.