Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete

Item number
1.3
Priced inputs
2
Derived rate
169.40 / tonne

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.3 Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete — is derived from 2 priced inputs and works out to ₹169.40 per tonne after water charges, GST, CPOH and cess. The full build-up is below.

  • Details of 23 tonnes of cement
  • Sundries Add for sweeping the wagon,
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday3.75736.002,760.00
9999screening the swept cement and filling the same in bagsMaterialL.S.2.622.275.95
TOTAL
2,765.95
Add GST on “X” (multiplying factor 0.2127)
588.32
TOTAL
3,354.27
Add 15% CPOH on “Y”
503.14
TOTAL
3,857.41
Add Cess @ 1% on “Z”
38.57
Cost of 23 tonne
3,895.98
Cost of 1 tonne
169.39
Say
169.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 114. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works