CPWD Analysis of Rates · Carriage of Materials

Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead upto 10 km for all lifts, complete as per directions of Engineer-in-charge. Note - item to be applicable in urban areas having directions for restricted hours for movement/ plying of load carrying motor vehicle of 3.5 cum or more

Item number
1.1.18
Analysis basis
Details of cost for 3.00 tirps of 8 cum capacity.
Priced inputs
3
Derived rate
494.10 / tirps

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 1.1.18 Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to approved municipal dumping ground for lead upto 10 km for all lifts, complete as per directions of Engineer-in-charge. Note - item to be applicable in urban areas having directions for restricted hours for movement/ plying of load carrying motor vehicle of 3.5 cum or more — is derived from 3 priced inputs for 3.00 tirps and works out to ₹494.10 per tirps after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0084Hire charges of Diesel Truck - 9 tonne excluding diesel & mobile oilHire charges of diesel truck - 9 tonne (witout POL)Machineryday12,250.002,250.00
0114BeldarLabourday6736.004,416.00
1235Diesel oilDieselMateriallitre19.5689.621,752.97
Total
8,418.97
Add GST on “X” (multiplying factor 0.2127)
1,790.71
TOTAL
10,209.68
Add 15% CPOH on “Y”
1,531.45
TOTAL
11,741.13
Add Cess @ 1% on “Z”
117.41
Cost for 3.00 trips of capacity 8 cum
11,858.54
Cost per trip of capacity per cum
494.11
Say
494.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 85. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.