Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete
- Item number
- 21.8.1
- Analysis basis
- 1 metre
- Priced inputs
- 4
- Derived rate
- ₹96.75/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.8.1 (Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete Upto 5mm depth and 5 mm width) is derived from 4 priced inputs for 1 metre and works out to ₹96.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- (i/c 5% wastage)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8646 | MAT | Silicon sealantWeather Silicon sealant | cartridge | 0.087 | 125.00 | 10.88 |
| 8654 | MAT | Masking tape | metre | 2 | 2.00 | 4.00 |
| 9999 | MAT | Sundries & profile | L.S. | 2.6 | 2.27 | 5.90 |
| 9999 | MAT | LABOUR | L.S. | 20.8 | 2.27 | 47.22 |
- TOTAL
- 68.00
- Add 1 % Water charges on “W”
- +0.68
- TOTAL
- 68.68
- Add GST on “X” (multiplying factor 0.2127)
- +14.61
- TOTAL
- 83.29
- Add 15% CPOH on “Y”
- +12.49
- TOTAL
- 95.78
- Add Cess @ 1% on “Z”
- +0.96
- Cost for 1 metre
- 96.74
- SAY
- ₹96.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1829
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1829. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.