Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete

Upto 5mm depth and 5 mm width
Item number
21.8.1
Analysis basis
1 metre
Priced inputs
4
Derived rate
₹96.75/ METRE
D-01/RATE ANALYSISITEM 21.8.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.8.1 (Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete Upto 5mm depth and 5 mm width) is derived from 4 priced inputs for 1 metre and works out to ₹96.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i/c 5% wastage)
ANALYSIS OF RATES · ITEM 21.8.1DETAILS OF COST FOR 1 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8646MATSilicon sealantWeather Silicon sealantcartridge0.087125.0010.88
8654MATMasking tapemetre22.004.00
9999MATSundries & profileL.S.2.62.275.90
9999MATLABOURL.S.20.82.2747.22
BUILD-UP TO RATE
TOTAL
68.00
Add 1 % Water charges on “W”
+0.68
TOTAL
68.68
Add GST on “X” (multiplying factor 0.2127)
+14.61
TOTAL
83.29
Add 15% CPOH on “Y”
+12.49
TOTAL
95.78
Add Cess @ 1% on “Z”
+0.96
Cost for 1 metre
96.74
SAY
₹96.75
D-02/SOURCEPRINTED PAGE 1829
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1829

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1829. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.