CPWD Analysis of Rates · Aluminium Work

Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete

Upto 5mm depth and 5 mm width

Item number
21.8.1
Analysis basis
Details of cost for 1 metre
Priced inputs
4
Derived rate
96.75 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.8.1 Filling the gap in between aluminium frame & adjacent RCC/ Brick/ Stone work by providing weather silicon sealant over backer rod of approved quality as per architectural drawings and direction of Engineer-in-charge complete Upto 5mm depth and 5 mm width — is derived from 4 priced inputs for 1 metre and works out to ₹96.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (i/c 5% wastage)
CodeInputUnitQuantityRate (INR)Amount (INR)
8646Silicon sealantWeather Silicon sealantMaterialcartridge0.087125.0010.88
8654Masking tapeMaterialmetre22.004.00
9999Sundries & profileMaterialL.S.2.62.275.90
9999LABOURMaterialL.S.20.82.2747.22
TOTAL
68.00
Add 1 % Water charges on “W”
0.68
TOTAL
68.68
Add GST on “X” (multiplying factor 0.2127)
14.61
TOTAL
83.29
Add 15% CPOH on “Y”
12.49
TOTAL
95.78
Add Cess @ 1% on “Z”
0.96
Cost for 1 metre
96.74
Say
96.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1829. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.