CPWD Analysis of Rates · Aluminium Work

Providing and fixing double action hydraulic floor spring of approved brand and manufacture conforming to IS : 6315, having brand logo embossed on the body / plate with double spring mechanism and door weight upto 125 kg, for doors, including cost of cutting floors, embedding in floors as required and making good the same matching to the existing floor finishing and cover plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the direction of Engineer-in-charge

With stainless steel cover plate minimum 1.25 mm thickness

Item number
21.4.1
Analysis basis
Details of cost for one number
Priced inputs
8
Derived rate
2,823.85 / one number

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.4.1 Providing and fixing double action hydraulic floor spring of approved brand and manufacture conforming to IS : 6315, having brand logo embossed on the body / plate with double spring mechanism and door weight upto 125 kg, for doors, including cost of cutting floors, embedding in floors as required and making good the same matching to the existing floor finishing and cover plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the direction of Engineer-in-charge With stainless steel cover plate minimum 1.25 mm thickness — is derived from 8 priced inputs for one number and works out to ₹2,823.85 per one number after water charges, GST, CPOH and cess. The full build-up is below.

  • Cement concrete 1:2:4
CodeInputUnitQuantityRate (INR)Amount (INR)
7394Double action hydraulic floor spring with stainless steel cover plateMaterialeach11,615.001,615.00
9977CARRIAGEMaterialL.S.132.2729.51
9999Sundries and screwsMaterialL.S.262.2759.02
Rate as per item no. 4.1.3 of SH : concrete workRate as per item 4.1.3Sub-analysiscum0.0027,878.5015.76
0123Mason 1st classMason 1st classLabourday0.08897.0071.76
0124Mason 2nd classMason 2nd classLabourday0.08816.0065.28
0112Carpenter 2nd classLabourday0.01816.008.16
0114BeldarLabourday0.17736.00125.12
TOTAL
1,989.61
Add 1 % Water charges on “W-A”
19.74
TOTAL
2,009.35
Add GST on “X-A” (multiplying factor 0.2127)
424.04
TOTAL
2,433.39
Add 15% CPOH on “Y-A”
362.64
TOTAL
2,796.03
Add Cess @ 1% on “Z-A”
27.80
Cost for each
2,823.83
Say
2,823.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1825. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works