CPWD Analysis of Rates · Aluminium Work
Providing and fixing double action hydraulic floor spring of approved brand and manufacture conforming to IS : 6315, having brand logo embossed on the body / plate with double spring mechanism and door weight upto 125 kg, for doors, including cost of cutting floors, embedding in floors as required and making good the same matching to the existing floor finishing and cover plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the direction of Engineer-in-charge
With stainless steel cover plate minimum 1.25 mm thickness
- Item number
- 21.4.1
- Analysis basis
- Details of cost for one number
- Priced inputs
- 8
- Derived rate
- ₹2,823.85 / one number
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.4.1 — Providing and fixing double action hydraulic floor spring of approved brand and manufacture conforming to IS : 6315, having brand logo embossed on the body / plate with double spring mechanism and door weight upto 125 kg, for doors, including cost of cutting floors, embedding in floors as required and making good the same matching to the existing floor finishing and cover plates with brass pivot and single piece M.S. sheet outer box with slide plate etc. complete as per the direction of Engineer-in-charge With stainless steel cover plate minimum 1.25 mm thickness — is derived from 8 priced inputs for one number and works out to ₹2,823.85 per one number after water charges, GST, CPOH and cess. The full build-up is below.
- Cement concrete 1:2:4
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7394 | Double action hydraulic floor spring with stainless steel cover plateMaterial | each | 1 | 1,615.00 | 1,615.00 |
| 9977 | CARRIAGEMaterial | L.S. | 13 | 2.27 | 29.51 |
| 9999 | Sundries and screwsMaterial | L.S. | 26 | 2.27 | 59.02 |
| Rate as per item no. 4.1.3 of SH : concrete workRate as per item 4.1.3Sub-analysis | cum | 0.002 | 7,878.50 | 15.76 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.08 | 897.00 | 71.76 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.08 | 816.00 | 65.28 |
| 0112 | Carpenter 2nd classLabour | day | 0.01 | 816.00 | 8.16 |
| 0114 | BeldarLabour | day | 0.17 | 736.00 | 125.12 |
- TOTAL
- 1,989.61
- Add 1 % Water charges on “W-A”
- 19.74
- TOTAL
- 2,009.35
- Add GST on “X-A” (multiplying factor 0.2127)
- 424.04
- TOTAL
- 2,433.39
- Add 15% CPOH on “Y-A”
- 362.64
- TOTAL
- 2,796.03
- Add Cess @ 1% on “Z-A”
- 27.80
- Cost for each
- 2,823.83
- Say
- 2,823.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1825. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.