Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item)

With float glass panes of 8 mm thickness (weight not less than 20 kg/sqm)
Item number
21.3.3
Analysis basis
1.00 sqm
Priced inputs
6
Derived rate
₹1,685.40/ SQM
D-01/RATE ANALYSISITEM 21.3.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.3.3 (Providing and fixing glazing in aluminium door, window, ventilator shutters and partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall be paid in basic item): With float glass panes of 8 mm thickness (weight not less than 20 kg/sqm)) is derived from 6 priced inputs for 1.00 sqm and works out to ₹1,685.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Float Glass panes 8.0 mm thick = 1.00 sqm
  • sqm
  • Total =1.10 sqm
  • Add for wastage & breakage @ 10% = 0.10
ANALYSIS OF RATES · ITEM 21.3.3DETAILS OF COST FOR 1.00 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2408MATFloat glass sheet of nominal thickness 8 mm.(- weight not less than 20.00 kg/sqm)Float glass panes of nominal thickness 8 mm (weight not less than 20.00 kg/sqm)sqm1.1641.00705.10
9977MATCarriage of glassL.S.4.842.2710.99
7390MATNeoprene/EPDM rubber gasketEPDM Gasket for uPVC window/doormetre616.0096.00
0112LABCarpenter 2nd classday0.23816.00187.68
0114LABBeldarday0.23736.00169.28
9988MATSundries and carriage of gasketL.S.6.892.2715.64
BUILD-UP TO RATE
TOTAL
1,184.69
Add 1 % Water charges on “W”
+11.85
TOTAL
1,196.54
Add GST on “X” (multiplying factor 0.2127)
+254.50
TOTAL
1,451.04
Add 15% CPOH on “Y”
+217.66
TOTAL
1,668.70
Add Cess @ 1% on “Z”
+16.69
Cost for 1 sqm
1,685.39
SAY
₹1,685.40
D-02/SOURCEPRINTED PAGE 1824
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1824

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1824. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.