Providing and fixing aluminium round shape handle of outer dia 100 mm with SS screws etc. complete as per direction of Engineer-in-charge

Anodized (AC 15 ) aluminium
Item number
21.16.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹107.90/ NOS
D-01/RATE ANALYSISITEM 21.16.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.16.1 (Providing and fixing aluminium round shape handle of outer dia 100 mm with SS screws etc. complete as per direction of Engineer-in-charge Anodized (AC 15 ) aluminium) is derived from 4 priced inputs for 10 nos and works out to ₹107.90 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 21.16.1DETAIL OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8663MATAluminium round shape handle (anodised AC 15) outer dia 100mmAluminium round shape handle (anodised AC 15) outer dia 100 mmeach1068.00680.00
8666MATStainless steel screws 25 mm x4 mm100 Nos0.446.0018.40
0111LABCarpenter 1st classday0.06897.0053.82
9977MATCarriage of materialsL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
758.42
Add 1 % Water charges on “W”
+7.58
TOTAL
766.00
Add GST on “X” (multiplying factor 0.2127)
+162.93
TOTAL
928.93
Add 15% CPOH on “Y”
+139.34
TOTAL
1,068.27
Add Cess @ 1% on “Z”
+10.68
Cost of 10 nos
1,078.95
Cost of 1 nos
107.90
SAY
₹107.90
D-02/SOURCEPRINTED PAGE 1837
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1837

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1837. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.