Providing and fixing aluminium casement windows fastener of required length for aluminium windows with necessary screws etc. complete

Polyester powder coated minimum thickness 50 micron aluminium
Item number
21.15.3
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹95.10/ NOS
D-01/RATE ANALYSISITEM 21.15.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.15.3 (Providing and fixing aluminium casement windows fastener of required length for aluminium windows with necessary screws etc. complete Polyester powder coated minimum thickness 50 micron aluminium) is derived from 4 priced inputs for 10 nos and works out to ₹95.10 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 21.15.3DETAIL OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8662MATAluminium casement window fastener (polyester powder coated)each1059.00590.00
8666MATStainless steel screws 25 mm x4 mm100 Nos0.446.0018.40
0111LABCarpenter 1st classday0.06897.0053.82
9977MATCarriage of materialsL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
668.42
Add 1 % Water charges on “W”
+6.68
TOTAL
675.10
Add GST on “X” (multiplying factor 0.2127)
+143.59
TOTAL
818.69
Add 15% CPOH on “Y”
+122.80
TOTAL
941.49
Add Cess @ 1% on “Z”
+9.41
Cost of 10 nos
950.90
Cost of 1 nos
95.09
SAY
₹95.10
D-02/SOURCEPRINTED PAGE 1837
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1837

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1837. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.