Providing and fixing stainless steel (SS 304 grade) adjustable friction windows stays of approved quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-in-charge complete

255 X 19 mm
Item number
21.11.2
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹387.00/ NOS
D-01/RATE ANALYSISITEM 21.11.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.11.2 (Providing and fixing stainless steel (SS 304 grade) adjustable friction windows stays of approved quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-in-charge complete 255 X 19 mm) is derived from 5 priced inputs for 10 nos and works out to ₹387.00 each after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 21.11.2DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8650MATStainless steel (SS 304 grade) adjustable 255 x 19mmStainless steel (SS 304 grade) adjustable friction window stay 255 x 19 mmeach10248.002,480.00
8647MATStainless steel screws 30 mm x4 mm100 nos0.442.0016.80
9977MATCARRIAGEL.S.2.732.276.20
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.14736.00103.04
BUILD-UP TO RATE
TOTAL
2,720.28
Add 1 % Water charges on “W”
+27.20
TOTAL
2,747.48
Add GST on “X” (multiplying factor 0.2127)
+584.39
TOTAL
3,331.87
Add 15% CPOH on “Y”
+499.78
TOTAL
3,831.65
Add Cess @ 1% on “Z”
+38.32
Cost for 10 nos
3,869.97
Cost for each
387.00
SAY
₹387.00
D-02/SOURCEPRINTED PAGE 1832
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1832

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1832. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSALUMINIUM WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.