Providing and fixing stainless steel (SS 304 grade) adjustable friction windows stays of approved quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-in-charge complete
- Item number
- 21.11.1
- Analysis basis
- 10 nos
- Priced inputs
- 5
- Derived rate
- ₹344.30/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 21.11.1 (Providing and fixing stainless steel (SS 304 grade) adjustable friction windows stays of approved quality with necessary stainless steel screws etc. to the side hung windows as per direction of Engineer-in-charge complete 205 X 19 mm) is derived from 5 priced inputs for 10 nos and works out to ₹344.30 each after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8649 | MAT | Stainless steel (SS 304 grade) adjustable friction window stay 205 x 19 mm | each | 10 | 218.00 | 2,180.00 |
| 8647 | MAT | Stainless steel screws 30 mm x4 mm | 100 nos | 0.4 | 42.00 | 16.80 |
| 9977 | MAT | CARRIAGE | L.S. | 2.73 | 2.27 | 6.20 |
| 0112 | LAB | Carpenter 2nd class | day | 0.14 | 816.00 | 114.24 |
| 0114 | LAB | Beldar | day | 0.14 | 736.00 | 103.04 |
- TOTAL
- 2,420.28
- Add 1 % Water charges on “W”
- +24.20
- TOTAL
- 2,444.48
- Add GST on “X” (multiplying factor 0.2127)
- +519.94
- TOTAL
- 2,964.42
- Add 15% CPOH on “Y”
- +444.66
- TOTAL
- 3,409.08
- Add Cess @ 1% on “Z”
- +34.09
- Cost for 10 nos
- 3,443.17
- Cost for each
- 344.32
- SAY
- ₹344.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1831
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1831. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.