Providing and fixing bright finished brass handles with screws etc. complete
- Item number
- 9.81.3
- Analysis basis
- 10 nos
- Priced inputs
- 4
- Derived rate
- ₹184.95/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.81.3 (Providing and fixing bright finished brass handles with screws etc. complete: 75 mm) is derived from 4 priced inputs for 10 nos and works out to ₹184.95 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0410 | MAT | Brass handles75 mm with plate 125x32 mmBrass handles 75 mm with plate 125x32 mm | each | 10 | 120.00 | 1,200.00 |
| 0452 | MAT | Brass screws 25 mm | 100 Nos | 0.4 | 110.00 | 44.00 |
| 9977 | MAT | Carriage of material | L.S. | 0.91 | 2.27 | 2.07 |
| 0111 | LAB | Carpenter 1st class | day | 0.06 | 897.00 | 53.82 |
- TOTAL
- 1,299.89
- Add 1 % Water charges on “W”
- +13.00
- TOTAL
- 1,312.89
- Add GST on “X” (multiplying factor 0.2127)
- +279.25
- TOTAL
- 1,592.14
- Add 15% CPOH on “Y”
- +238.82
- TOTAL
- 1,830.96
- Add Cess @ 1% on “Z”
- +18.31
- Cost of 10 nos
- 1,849.27
- Cost of 1 no
- 184.93
- SAY
- ₹184.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 548
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 548. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.