Providing and fixing special quality bright finished brass cupboard or ward robe locks with four levers of approved quality including necessary screws etc. complete
- Item number
- 9.79.3
- Analysis basis
- one No
- Priced inputs
- 3
- Derived rate
- ₹362.40/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.79.3 (Providing and fixing special quality bright finished brass cupboard or ward robe locks with four levers of approved quality including necessary screws etc. complete 65 mm) is derived from 3 priced inputs for one No and works out to ₹362.40 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2453 | MAT | Brass cupboard lock 6 levers (best make of approved quality) 65 mm sizeBrass cupboard lock 6 levers of approved quality, 65 mm size | each | 1 | 94.00 | 94.00 |
| 0111 | LAB | Carpenter 1st class | day | 0.17 | 897.00 | 152.49 |
| 9999 | MAT | Sundries & screws | L.S. | 3.64 | 2.27 | 8.26 |
- TOTAL
- 254.75
- Add 1 % Water charges on “W”
- +2.55
- TOTAL
- 257.30
- Add GST on “X” (multiplying factor 0.2127)
- +54.73
- TOTAL
- 312.03
- Add 15% CPOH on “Y”
- +46.80
- TOTAL
- 358.83
- Add Cess @ 1% on “Z”
- +3.59
- Cost of 1 no
- 362.42
- SAY
- ₹362.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 546
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 546. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.