Providing and fixing special quality bright finished brass cupboard or ward robe locks with four levers of approved quality including necessary screws etc. complete

65 mm
Item number
9.79.3
Analysis basis
one No
Priced inputs
3
Derived rate
₹362.40/ NO
D-01/RATE ANALYSISITEM 9.79.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.79.3 (Providing and fixing special quality bright finished brass cupboard or ward robe locks with four levers of approved quality including necessary screws etc. complete 65 mm) is derived from 3 priced inputs for one No and works out to ₹362.40 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.79.3DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2453MATBrass cupboard lock 6 levers (best make of approved quality) 65 mm sizeBrass cupboard lock 6 levers of approved quality, 65 mm sizeeach194.0094.00
0111LABCarpenter 1st classday0.17897.00152.49
9999MATSundries & screwsL.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
254.75
Add 1 % Water charges on “W”
+2.55
TOTAL
257.30
Add GST on “X” (multiplying factor 0.2127)
+54.73
TOTAL
312.03
Add 15% CPOH on “Y”
+46.80
TOTAL
358.83
Add Cess @ 1% on “Z”
+3.59
Cost of 1 no
362.42
SAY
₹362.40
D-02/SOURCEPRINTED PAGE 546
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
546

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 546. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.