Providing and fixing bright finished brass 100 mm mortice latch with one dead bolt and a pair of lever handles of approved quality with necessary screws etc. complete

Item number
9.77
Analysis basis
one No
Priced inputs
3
Derived rate
₹726.60/ NO
D-01/RATE ANALYSISITEM 9.77

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.77 (Providing and fixing bright finished brass 100 mm mortice latch with one dead bolt and a pair of lever handles of approved quality with necessary screws etc. complete) is derived from 3 priced inputs for one No and works out to ₹726.60 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.77DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0414MATBrass mortice latch 100x65mm with a pair of brass lever handlesBrass mortice latch 100x65 mm with a pair of brass lever handleseach1350.00350.00
0111LABCarpenter 1st classday0.17897.00152.49
9999MATSundries (screws, carriage etc.)L.S.3.642.278.26
BUILD-UP TO RATE
TOTAL
510.75
Add 1 % Water charges on “W”
+5.11
TOTAL
515.86
Add GST on “X” (multiplying factor 0.2127)
+109.72
TOTAL
625.58
Add 15% CPOH on “Y”
+93.84
TOTAL
719.42
Add Cess @ 1% on “Z”
+7.19
Cost of 1 no
726.61
SAY
₹726.60
D-02/SOURCEPRINTED PAGE 544
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
544

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 544. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.