R/DAR 2023

Providing and fixing bright finished brass door latch with necessary screws etc. complete

300x16x5 mm
Item number
9.75.1
Analysis basis
10 nos
Priced inputs
4
Derived rate
₹322.20/ NO
D-01/RATE ANALYSISITEM 9.75.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.75.1 (Providing and fixing bright finished brass door latch with necessary screws etc. complete : 300x16x5 mm) is derived from 4 priced inputs for 10 nos and works out to ₹322.20 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.75.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0411MATBrass door latch 300x16x5 mm (0.380 kg)Brass door latch 300x16x5 mm weighing not less than 0.380 kgeach10205.002,050.00
0452MATBrass screws 25 mm100 Nos0.9110.0099.00
9977MATCarriage of materialsL.S.3.642.278.26
0111LABCarpenter 1st classday0.12897.00107.64
BUILD-UP TO RATE
TOTAL
2,264.90
Add 1 % Water charges on “W”
+22.65
TOTAL
2,287.55
Add GST on “X” (multiplying factor 0.2127)
+486.56
TOTAL
2,774.11
Add 15% CPOH on “Y”
+416.12
TOTAL
3,190.23
Add Cess @ 1% on “Z”
+31.90
Cost of 10 nos.
3,222.13
Cost of 1 no.
322.21
SAY
₹322.20
D-02/SOURCEPRINTED PAGE 542
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
542

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 542. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.