Providing and fixing bright finished brass butt hinges with necessary screws etc. complete

75x65x4 mm (heavy type)
Item number
9.72.5
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹173.40/ NO
D-01/RATE ANALYSISITEM 9.72.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.72.5 (Providing and fixing bright finished brass butt hinges with necessary screws etc. complete : 75x65x4 mm (heavy type)) is derived from 5 priced inputs for 10 nos and works out to ₹173.40 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.72.5DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0384MATBrass butt hinges (heavy type) : 75x65x4.0 mm(0.20 kg)Brass butt hinges (heavy type) :75x65x4.0 mm (weighing not less than 0.20 kg)10 Nos1921.00921.00
0451MATBrass screws 30 mm100 Nos0.6154.0092.40
9977MATCarriage of materialL.S.2.732.276.20
0111LABCarpenter 1st classday0.14897.00125.58
0114LABBeldarday0.1736.0073.60
BUILD-UP TO RATE
TOTAL
1,218.78
Add 1 % Water charges on “W”
+12.19
TOTAL
1,230.97
Add GST on “X” (multiplying factor 0.2127)
+261.83
TOTAL
1,492.80
Add 15% CPOH on “Y”
+223.92
TOTAL
1,716.72
Add Cess @ 1% on “Z”
+17.17
Cost for 10 nos.
1,733.89
Cost of 1 no.
173.39
SAY
₹173.40
D-02/SOURCEPRINTED PAGE 537
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
537

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 537. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.