Providing and fixing bright finished brass butt hinges with necessary screws etc. complete

125x70x4 mm (ordinary type)
Item number
9.72.2
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹185.15/ NO
D-01/RATE ANALYSISITEM 9.72.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.72.2 (Providing and fixing bright finished brass butt hinges with necessary screws etc. complete : 125x70x4 mm (ordinary type)) is derived from 5 priced inputs for 10 nos and works out to ₹185.15 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.72.2DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0378MATBrass butt hinges (light/ordinary type) : 125x70x4 mm10 Nos1852.00852.00
0449MATBrass screws 50 mm100 Nos1242.00242.00
9977MATCarriage of materialL.S.3.642.278.26
0111LABCarpenter 1st classday0.14897.00125.58
0114LABBeldarday0.1736.0073.60
BUILD-UP TO RATE
TOTAL
1,301.44
Add 1 % Water charges on “W”
+13.01
TOTAL
1,314.45
Add GST on “X” (multiplying factor 0.2127)
+279.58
TOTAL
1,594.03
Add 15% CPOH on “Y”
+239.10
TOTAL
1,833.13
Add Cess @ 1% on “Z”
+18.33
Cost for 10 nos.
1,851.46
Cost of 1 no.
185.15
SAY
₹185.15
D-02/SOURCEPRINTED PAGE 535
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
535

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 535. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.