Skip to main content
R/DAR 2023

Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight) with stainless steel screws etc. complete

125x64x2.50 mm
Item number
9.71.1
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹129.85/ NO
D-01/RATE ANALYSISITEM 9.71.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.71.1 (Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight) with stainless steel screws etc. complete : 125x64x2.50 mm) is derived from 5 priced inputs for 10 nos and works out to ₹129.85 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.71.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8219MATStainless steel butt hinges (heavy weight) 125x64x2.5 mm IS : 12817 markedStainless steel butt hinges (heavy weight) 125x64x2.5 mm IS :12817 marked10 Nos1470.00470.00
8210MATStainless steel screws 50 mm100 Nos0.8320.00256.00
9977MATCarriage of materialsL.S.2.732.276.20
0112LABCarpenter 2nd classday0.14816.00114.24
0114LABBeldarday0.09736.0066.24
BUILD-UP TO RATE
TOTAL
912.68
Add 1 % Water charges on “W”
+9.13
TOTAL
921.81
Add GST on “X” (multiplying factor 0.2127)
+196.07
TOTAL
1,117.88
Add 15% CPOH on “Y”
+167.68
TOTAL
1,285.56
Add Cess @ 1% on “Z”
+12.86
Cost of 10 nos.
1,298.42
Cost of 1 no
129.84
SAY
₹129.85
D-02/SOURCEPRINTED PAGE 533
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
533

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 533. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.