R/DAR 2023

Providing and fixing ISI marked oxidised M.S. sliding door bolts with nuts and screws etc. complete (Copper oxidised as per IS 1378)

300x16 mm
Item number
9.62.1
Analysis basis
10 nos
Priced inputs
5
Derived rate
₹216.55/ NO
D-01/RATE ANALYSISITEM 9.62.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.62.1 (Providing and fixing ISI marked oxidised M.S. sliding door bolts with nuts and screws etc. complete (Copper oxidised as per IS 1378) 300x16 mm) is derived from 5 priced inputs for 10 nos and works out to ₹216.55 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.62.1DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0660MATOxidised mild steel sliding door bolt 300x16 mmeach10100.001,000.00
7040MATOxidised mild steel screws 35 mm100 Nos1.253.0063.60
0641MATBright finished or black enamelled mild steel bolts and nuts 50x6 mmBright finished or black enameled mild steel bolts and nuts 50x6 mmeach406.00240.00
9988MATCarriage of materials & sundriesL.S.6.372.2714.46
0112LABCarpenter 2nd classday0.25816.00204.00
BUILD-UP TO RATE
TOTAL
1,522.06
Add 1 % Water charges on “W”
+15.22
TOTAL
1,537.28
Add GST on “X” (multiplying factor 0.2127)
+326.98
TOTAL
1,864.26
Add 15% CPOH on “Y”
+279.64
TOTAL
2,143.90
Add Cess @ 1% on “Z”
+21.44
Cost of 10 nos.
2,165.34
Cost of 1 no.
216.53
SAY
₹216.55
D-02/SOURCEPRINTED PAGE 522
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
522

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 522. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.